11251 S COMPTON AVE 90059
Certificate Information: 11251 S COMPTON AVE 90059
- Application / Permit
- 22020-10000-01527
- Plan Check / Job No.
- B22LA12938
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (4) Park or Playground operated by governmental agency
- Work Description
- ePLAN. RENOVATION OF (E) PLAYGROUND FACILITY, REMOVE PLAYGROUND AND HARDSCAPE, GRADING, NEW HARDSCAPE AND PLAYGROUND SURFACING, WATER MISTING AREA, LANDSCAPING (INCLUDING IRRIGATION), LID INFILTRATION PLANTERS, AND RESURFACING OF THE ADJACENT SPORTS COURT
- Permit Issued
- Issued on 5/2/2023
- Issuing Office
- Current Status
- Permit Finaled on 8/14/2023
Permit Application Status History
| Submitted | 7/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | LAMAR DAVIS |
| Corrections Issued | 8/8/2022 | LAMAR DAVIS |
| Quality Review Completed | 8/9/2022 | GARO TELMI |
| Plan Check Approved | 3/20/2023 | CRYSTEL MAALOUF |
| Issued | 5/2/2023 | APPLICANT |
| Permit Finaled | 8/11/2023 | ALAN MORELOS |
Permit Application Clearance Information
| Historic monument | Cleared | 8/24/2022 | MAX LODER |
| City owned building/parcel | Cleared | 9/6/2022 | LAMAR DAVIS |
| DAS Clearance | Cleared | 10/27/2022 | FARUK SEZER |
| Low Impact Development | Cleared | 3/6/2023 | AMMAR ELTAWIL |
Contact Information
| Architect | , ; Lic. No.: C34421 | , |
| Contractor | Kompan California Inc; Lic. No.: 1072215-A | ONE CAPITOL MALL STE 670 SACRAMENTO, CA 95814 |
| Engineer | Dhungana,, Ishwar; Lic. No.: C77744 | 12463 GARDEN PKWY SANTA FE SPRINGS, CA 90670 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/5/2023 | Approved | ALAN MORELOS |
| Footing/Foundation/Slab | 6/9/2023 | Conditional Approval | DARRYL ARNOLD |
| Pre-Inspection | 6/9/2023 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 6/21/2023 | Approved | ALAN MORELOS |
| Excavation/Setback/Form/Re-Bar | 7/3/2023 | Approved | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 7/3/2023 | Approved | MARTIN TAVITIAN |
| Pre-Inspection | 7/21/2023 | Partial Approval | MARTIN TAVITIAN |
| Final | 7/28/2023 | Conditional Approval | DARRYL ARNOLD |
| Final | 8/11/2023 | Permit Finaled | ALAN MORELOS |