9482 W LLOYDCREST DR 90210

Certificate Information: 9482 W LLOYDCREST DR 90210

Application / Permit
22020-10000-01416
Plan Check / Job No.
B21LA19248
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
(N) TWO RETAINING WALLS
Permit Issued
Issued on 8/6/2025
Issuing Office
Valley
Current Status
Issued on 8/6/2025

Permit Application Status History

Submitted 10/13/2021 APPLICANT
Assigned to Plan Check Engineer 10/28/2021 DANIEL YIP
Corrections Issued 11/1/2021 DANIEL YIP
Quality Review Completed 11/9/2021 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 11/10/2021 APPLICANT
Applicant returned to address corrections 6/27/2022 DANIEL YIP
Plan Check Approved 2/6/2025 DANIEL YIP
Issued 8/6/2025 APPLICANT

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Eldav Construction & Development Inc; Lic. No.: 949125-B 19562 VENTURA BLVD #223      TARZANA, CA 91356
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

ROBERT PINA, (213) 482-0404 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Other (see comments) 9/18/2025 Approved ROBERT PINA
Piling/Pier/Caisson 9/18/2025 Conditional Approval ROBERT PINA
Deputy Grading 9/19/2025 Approved ROBERT PINA
Deputy Reinf. Concrete 9/22/2025 Approved ROBERT PINA
Piling/Pier/Caisson 9/22/2025 Conditional Approval ROBERT PINA
Deputy Grading 9/25/2025 Approved ROBERT PINA
Deputy Grading 9/26/2025 Corrections Issued ROBERT PINA
Deputy Reinf. Concrete 9/29/2025 Approved ROBERT PINA
Deputy Grading 9/30/2025 Approved ROBERT PINA
Deputy Grading 10/1/2025 Approved ROBERT PINA
Deputy Reinf. Concrete 10/6/2025 Approved ROBERT PINA
Deputy Reinf. Concrete 10/8/2025 Approved ROBERT PINA
Deputy Drilled-In Anchors 10/14/2025 No Access for Inspection ROBERT PINA
Deputy Shotcrete 11/10/2025 No Access for Inspection MICHAEL TEMPLE
Reinforced Concrete Frame 11/14/2025 Not Ready for Inspection ROBERT PINA
Reinforced Concrete Frame 11/17/2025 Approved ROBERT PINA
Masonry Wall/Backfill 11/21/2025 Conditional Approval ROBERT PINA
Excavation/Setback/Form/Re-Bar 11/26/2025 Approved ROBERT PINA
Footing/Foundation/Slab 2/3/2026 Approved ROBERT PINA
Excavation/Setback/Form/Re-Bar 2/6/2026 Conditional Approval ROBERT PINA
Excavation/Setback/Form/Re-Bar 2/9/2026 Partial Approval JONATHAN HOM