2856 W SUNSET BLVD 90026
Certificate Information: 2856 W SUNSET BLVD 90026
- Application / Permit
- 22020-10000-01394
- Plan Check / Job No.
- B22LA11879
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- Change of use from retail to retail with wine sales with accessory wine tasting area (150 square feet) per ZA-2021-6348-CUB.
- Permit Issued
- Issued on 12/4/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/21/2022 | JOE VO |
| Corrections Issued | 6/23/2022 | JOE VO |
| Applicant returned to address corrections | 5/30/2023 | DANIEL SMILEY |
| Plan Check Approved | 8/7/2023 | DANIEL SMILEY |
| Issued | 12/4/2023 | APPLICANT |
| CofO in Progress | 4/17/2024 | RAFAEL CORTES |
| CofO Issued | 4/30/2024 | ERNESTO CORRAL |
| Permit Finaled | 4/30/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| ZA Case | Cleared | 1/11/2023 | RONY GIRON |
| ZA Case | Cleared | 5/31/2023 | EDWIN CANO |
| ZA Case | Cleared | 5/31/2023 | EDWIN CANO |
| "Q" conditions | Cleared | 7/25/2023 | CLAUDE GOODING |
| Comm Cor/Mini-Mall | Cleared | 7/25/2023 | CLAUDE GOODING |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2023 | CINDY QI |
| Sewer availability | Cleared | 7/31/2023 | CINDY QI |
| Food establishment approval | Cleared | 8/7/2023 | LACDHS APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 3/11/2024 | Not Ready for Inspection | RAFAEL CORTES |
| METHANE-Final | 3/11/2024 | Approved | RAFAEL CORTES |
| METHANE-Rough | 3/11/2024 | Approved | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 3/11/2024 | SGSOV Not Ready | RAFAEL CORTES |
| Smoke Detectors | 3/11/2024 | Approved | RAFAEL CORTES |
| Wood Frame | 3/11/2024 | Approved | RAFAEL CORTES |
| Final | 4/16/2024 | OK to Issue CofO | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 4/16/2024 | SGSOV Approved | RAFAEL CORTES |