16180 W MULHOLLAND DR 90049
Certificate Information: 16180 W MULHOLLAND DR 90049
- Application / Permit
- 22020-10000-01278
- Plan Check / Job No.
- B22LA10828
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Patio Cover
- Work Description
- ePLAN. (N) SHADE STRUCTURE W/ FABRIC ROOF
- Permit Issued
- Issued on 8/16/2022
- Issuing Office
- Current Status
- CofO Issued on 9/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2022 | LAMAR DAVIS |
| Corrections Issued | 6/29/2022 | LAMAR DAVIS |
| Quality Review Completed | 7/6/2022 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 8/12/2022 | LAMAR DAVIS |
| Issued | 8/16/2022 | APPLICANT |
| Permit Finaled | 9/12/2024 | DAVID TSAU |
| CofO Issued | 9/12/2024 | DAVID TSAU |
| Permit Finaled | 9/12/2024 | DAVID TSAU |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/29/2022 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2022 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 8/3/2022 | DINAH GARIN |
| DAS Clearance | Cleared | 8/10/2022 | FARUK SEZER |
| CPC | Cleared | 8/12/2022 | JASON CHAN |
| CPC | Cleared | 8/12/2022 | JASON CHAN |
| Miscellaneous | Cleared | 8/12/2022 | JASON CHAN |
| Specific Plan | Cleared | 8/12/2022 | JASON CHAN |
| ZA Case | Cleared | 8/12/2022 | JASON CHAN |
Contact Information
| Architect | Jameson,, Craig Allen; Lic. No.: C30687 | 7225 CRESCENT PARK W #311 PLAYA VISTA, CA 90094 |
| Contractor | Shade Structures Inc; Lic. No.: 989458-B | P O BOX 3467 COPELL, TX 75019 |
| Engineer | Davis,, Richard Hays; Lic. No.: C48082 | 2015 CANTATA DR LOS ANGELES, CA 90068 |
| Engineer | Reynolds,, Aaron; Lic. No.: S4338 | 4022 JOELTON DRIVE AGOURA HILLS, CA 91301 |
Inspector Information
| DANIEL ARMENTA, (310) 914-3925 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 5/1/2023 | Not Ready for Inspection | DERRICK SPENCER |
| Footing/Foundation/Slab | 5/1/2023 | Approved | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 5/1/2023 | SGSOV Approved | DERRICK SPENCER |
| Smoke Detectors | 5/1/2023 | Approved | DERRICK SPENCER |
| Verify Sprinkler Sign Off | 5/1/2023 | Approved | DERRICK SPENCER |
| Wood Frame | 5/1/2023 | Approved | DERRICK SPENCER |
| Special/Order Compliance | 5/3/2023 | Partial Inspection | GRANT WOODS |
| Final | 9/9/2024 | Conditional Approval | GRANT WOODS |