4501 W COLORADO BLVD 90039
Certificate Information: 4501 W COLORADO BLVD 90039
- Application / Permit
- 22020-10000-01200
- Plan Check / Job No.
- B22LA10085
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (15) Tower
- Work Description
- FOUNDATION FOR NEW COOLING TOWER ADJACENT TO TWO NEW COOLING TOWERS. NEW COOLING TOWER WILL SUPPORT TAKEDA PHARMACEUTICAL CENTRAL UTILITY OPERATIONS PROJECT. PROJECT ALSO INCLUSED ASSOCIATED MECHANICAL, PLUMBING, AND ELECTRICAL EQUIPMENT.
- Permit Issued
- Issued on 11/4/2022
- Issuing Office
- Current Status
- Permit Finaled on 9/12/2023
Permit Application Status History
| Submitted | 5/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2022 | ARSALAN SHABESTARI |
| Corrections Issued | 6/17/2022 | ARSALAN SHABESTARI |
| Re-Submittal Required | 6/24/2022 | KEN GILL |
| Building Plans Picked Up | 8/2/2022 | APPLICANT |
| Re-Submitted | 8/3/2022 | KEN GILL |
| Corrections Issued 2 | 8/8/2022 | ARSALAN SHABESTARI |
| Submitted for Second Quality Review | 8/11/2022 | KEN GILL |
| Plan Check Approved | 10/3/2022 | ARSALAN SHABESTARI |
| Issued | 11/4/2022 | APPLICANT |
| Permit Finaled | 9/11/2023 | RONALD JIMENEZ |
Permit Application Clearance Information
| Metro Rail approval | Cleared | 8/16/2022 | ARSALAN SHABESTARI |
| ZI | Cleared | 9/8/2022 | ANACANY HURTADO |
| Miscellaneous | Cleared | 9/15/2022 | ANACANY HURTADO |
Contact Information
| Contractor | Dpr Construction A General Partnership; Lic. No.: 1083716-B | 1450 VETERANS BLVD REDWOOD CITY, CA 94063 |
| Engineer | Hoffmayer,, Joseph Julian; Lic. No.: S3935 | 5043 EVANWOOD AVENUE OAK PARK, CA 91377 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 3/23/2023 | Partial Approval | RONALD JIMENEZ |
| Excavation/Setback/Form/Re-Bar | 4/21/2023 | Partial Approval | RAFAEL CORTES |
| Footing/Foundation/Slab | 4/21/2023 | Partial Approval | RAFAEL CORTES |
| Footing/Foundation/Slab | 4/27/2023 | Partial Approval | RONALD JIMENEZ |
| Final | 8/8/2023 | Conditional Approval | RONALD JIMENEZ |
| Final | 9/11/2023 | Permit Finaled | RONALD JIMENEZ |