2211 N HOLLYRIDGE DR 90068
Certificate Information: 2211 N HOLLYRIDGE DR 90068
- Application / Permit
- 22020-10000-01193
- Plan Check / Job No.
- B22LA09960
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- CONSTRUCTION OF NEW RETAINING WALL 96'-6" LF (MAX. 6' HIGH) INCLUDING PILES AND GRADE BEAMS. 1 OF 3
- Permit Issued
- Issued on 6/5/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 9/26/2024
Permit Application Status History
| Submitted | 5/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2022 | CHUNG-WEN CHUANG |
| Corrections Issued | 7/6/2022 | CHUNG-WEN CHUANG |
| Quality Review Completed | 7/13/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 7/19/2022 | APPLICANT |
| Applicant returned to address corrections | 5/30/2023 | CHUNG-WEN CHUANG |
| Plan Check Approved | 5/31/2023 | CHUNG-WEN CHUANG |
| Issued | 6/5/2023 | APPLICANT |
| Permit Finaled | 9/25/2024 | CRAIG VAUGHAN |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 5/31/2023 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 5/31/2023 | CHUNG-WEN CHUANG |
Contact Information
| Architect | Bryant,, Charles Theodore; Lic. No.: C21528 | 110 TAOS ROAD ALTADENA, CA 91001 |
| Contractor | Owner-Builder | , |
| Engineer | Hayes,, Leonard C; Lic. No.: GE386 | 595 285 W IVINS, UT 84738 |
| Engineer | Obando,, Gaspar Eduardo; Lic. No.: C71382 | 3101 OCEAN PARK BLVD STE 100, PMB 122 SANTA MONICA, CA 90405 |
| Engineer | Onishi,, Robert K; Lic. No.: S3705 | 4438 LINDBLADE DRIVE LOS ANGELES, CA 90066 |
| Geologist | Miller,, Steven; Lic. No.: EG1303 | 23890 COPPERHILL DRIVE #111 VALENCIA, CA 91354 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 9/18/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Deputy Reinf. Concrete | 10/17/2023 | Conditional Approval | SCOTT FINNILA |
| Piling/Pier/Caisson | 10/17/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Reinf. Concrete | 10/25/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 11/13/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Deputy Reinf. Concrete | 11/15/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Reinf. Concrete | 12/1/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Reinf. Concrete | 1/23/2024 | Conditional Approval | BRIAN SULLIVAN |
| Final | 9/25/2024 | Permit Finaled | CRAIG VAUGHAN |