694 S OXFORD AVE 90005
Certificate Information: 694 S OXFORD AVE 90005
- Application / Permit
- 22020-10000-01057
- Plan Check / Job No.
- B19LA26788
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- (5)Five new architectural uncovered canopies.
- Permit Issued
- Issued on 8/9/2024
- Issuing Office
- Metro
- Current Status
- Issued on 8/9/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/19/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 2/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2020 | SAMUEL GONZALEZ |
| Corrections Issued | 2/21/2020 | SAMUEL GONZALEZ |
| Quality Review Completed | 2/24/2020 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 2/28/2020 | APPLICANT |
| Green Plans Picked Up | 8/19/2021 | APPLICANT |
| Applicant returned to address corrections | 1/19/2022 | SAMUEL GONZALEZ |
| Plan Check Approved | 6/3/2022 | SAMUEL GONZALEZ |
| Issued | 8/9/2024 | APPLICANT |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 5/19/2022 | DAVID URITA |
| Redevelopment Project Area | Cleared | 5/19/2022 | DAVID URITA |
Contact Information
| Architect | Kimm,, Alice Young; Lic. No.: C25438 | 1461 E 4TH ST LOS ANGELES, CA 90033 |
| Contractor | Ford E C Inc; Lic. No.: 396212-B | 10850 WILSHIRE BLVD 1120 LOS ANGELES, CA 90024 |
| Engineer | Youssef,, Nabih Fouad; Lic. No.: S2026 | 550 S HOPE ST STE 1700 LOS ANGELES, CA 90071 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/25/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 9/23/2025 | Partial Approval | JEROME BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 9/29/2025 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 10/1/2025 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 10/15/2025 | Partial Approval | JEROME BLACKWOOD |