9332 W NIGHTINGALE DR 90069

Certificate Information: 9332 W NIGHTINGALE DR 90069

Application / Permit
22020-10000-00991
Plan Check / Job No.
B22LA08340
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
New retaining wall to accomodate DWP trasnfromer
Permit Issued
Issued on 11/8/2022
Issuing Office
Metro
Current Status
Permit Finaled on 5/14/2026

Permit Application Status History

Submitted 5/3/2022 APPLICANT
Assigned to Plan Check Engineer 5/19/2022 MARCELA FRANQUEZ
Corrections Issued 5/26/2022 MARCELA FRANQUEZ
Quality Review Completed 6/2/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 6/16/2022 APPLICANT
Applicant returned to address corrections 8/3/2022 MARCELA FRANQUEZ
Applicant returned to address corrections 9/16/2022 MARCELA FRANQUEZ
Plan Check Approved 11/3/2022 MARCELA FRANQUEZ
Issued 11/8/2022 APPLICANT
Permit Finaled 5/13/2026 ROBERT PINA

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/11/2022 CINDY QI
Grading Pre-Inspection Cleared 9/8/2022 KIRK LINKLATER
Landscape for retaining wall Cleared 10/7/2022 MAYELA VILLA

Contact Information

Architect Bondanelli,, Bruno; Lic. No.: C29801 24139 AFAMADO LANE      DIAMOND BAR, CA 91765
Contractor T S D Corporation; Lic. No.: 675774-B 8800 VENICE BLVD SUITE 315      LOS ANGELES, CA 90034
Engineer Miller,, Karen Lynn; Lic. No.: GE2257 6634 VALJEAN AVENUE      VAN NUYS, CA 91406
Engineer Mina,, Joseph; Lic. No.: C53465 7247 DARNOCH WY      WEST HILLS, CA 91307
Engineer Obando,, Gaspar Eduardo; Lic. No.: C71382 3101 OCEAN PARK BLVD   STE 100, PMB 122    SANTA MONICA, CA 90405
Geologist Van, Meter, James L.; Lic. No.: EG2031 6634 VALJEAN AVE      VAN NUYS, CA 91406

Inspector Information

ROBERT PINA, (213) 482-0404 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/15/2023 Partial Inspection RAUL BARAJAS
Grading Pre-Inspection 3/24/2023 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 4/25/2025 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 4/29/2025 Approved ROBERT PINA
Footing/Foundation/Slab 5/5/2025 Conditional Approval ROBERT PINA
Final 5/13/2026 Permit Finaled ROBERT PINA