11100 W PEORIA ST 91352
Certificate Information: 11100 W PEORIA ST 91352
- Application / Permit
- 22020-10000-00967
- Plan Check / Job No.
- B22LA08076
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Fence Wall
- Work Description
- NEW LADWP/SITE SWITCH GEAR YARD ENCLOSURE ( 114'-0" X 25'-9") WITH MAX 12 FOOT HIGH CONCRETE WALL
- Permit Issued
- Issued on 7/28/2022
- Issuing Office
- Current Status
- Permit Finaled on 8/27/2024
Permit Application Status History
| Submitted | 4/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2022 | GARO TELMI |
| Corrections Issued | 6/1/2022 | GARO TELMI |
| Quality Review Completed | 6/3/2022 | KEN GILL |
| Building Plans Picked Up | 6/7/2022 | APPLICANT |
| Applicant returned to address corrections | 6/28/2022 | GARO TELMI |
| Plan Check Approved | 7/25/2022 | GARO TELMI |
| Issued | 7/28/2022 | APPLICANT |
| Permit Finaled | 8/27/2024 | DANNY RODRIGUEZ |
Permit Application Clearance Information
| CPC | Cleared | 6/13/2022 | ANNA VIDAL |
| Clean Up Green Up | Cleared | 6/13/2022 | ANNA VIDAL |
| Miscellaneous | Cleared | 6/13/2022 | ANNA VIDAL |
| Flood clearance | Cleared | 6/14/2022 | BRYAN GATHUKA |
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2022 | CARLOS AGUILERA |
| DAS Clearance | Cleared | 6/22/2022 | GARO TELMI |
| Grading Pre-Inspection | Cleared | 7/25/2022 | LANNY MERRICK |
Contact Information
| Architect | Bastien,, Gary L; Lic. No.: C11164 | 15661 RED HILL AVENUE SUITE 150 TUSTIN, CA 92780 |
| Contractor | Snyder Langston Llc; Lic. No.: 1019188-B | 17962 COWAN IRVINE, CA 92614 |
| Engineer | Benson,, Thomas Clifford; Lic. No.: GE2091 | 645 W LA CROSSE ST GLENDORA, CA 91741 |
| Engineer | Cocke,, David Winbern; Lic. No.: S3005 | 19210 S VERMONT AVENUE BLDNG B SUITE 210 GARDENA, CA 90248 |
Inspector Information
| JOHN KITCKO, (818) 374-1109 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/11/2022 | Partial Approval | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 10/11/2022 | Partial Approval | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 10/13/2022 | Partial Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 1/31/2023 | Partial Approval | DANNY RODRIGUEZ |
| Special/Order Compliance | 1/31/2023 | Partial Approval | STEVEN LEVITT |
| Footing/Foundation/Slab | 2/3/2023 | Partial Approval | DANNY RODRIGUEZ |
| Special/Order Compliance | 2/3/2023 | Partial Approval | STEVEN LEVITT |
| Reinforced Concrete Frame | 2/16/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Final | 2/16/2024 | Partial Inspection | DANNY RODRIGUEZ |