5420 N SUNSET AVE 90027
Certificate Information: 5420 N SUNSET AVE 90027
- Application / Permit
- 22020-10000-00918
- Plan Check / Job No.
- B22LA03293
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- PROPOSE 2200 ' LONG WITH MAX. 30' TEMPORARY SHORING WITH LAGGING & SOLDIER PILES FOR NEW 6 STORY TYPE IIIA MIXED USE APARTMENT BUILDING OVER 2 LEVEL TYPE IA SUBTERRANEAN PARKING GARAGE. PER ZA-2017-1083-MCUP-SPT-RDP-SPR
- Permit Issued
- Issued on 4/25/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 3/12/2026
Permit Application Status History
| Submitted | 3/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2022 | GARO TELMI |
| Disabled Access Plans Picked Up | 3/21/2022 | APPLICANT |
| Green Plans Picked Up | 3/30/2022 | APPLICANT |
| Corrections Issued | 4/22/2022 | GARO TELMI |
| Quality Review Completed | 4/27/2022 | KEN GILL |
| Building Plans Picked Up | 5/9/2022 | APPLICANT |
| Applicant returned to address corrections | 6/16/2022 | GARO TELMI |
| Applicant returned to address corrections | 6/22/2022 | GARO TELMI |
| Applicant returned to address corrections | 6/28/2022 | GARO TELMI |
| Applicant returned to address corrections | 8/3/2022 | GARO TELMI |
| Applicant returned to address corrections | 10/25/2022 | GARO TELMI |
| Applicant returned to address corrections | 12/13/2022 | GARO TELMI |
| Applicant returned to address corrections | 2/9/2023 | GARO TELMI |
| Applicant returned to address corrections | 4/3/2023 | GARO TELMI |
| Applicant returned to address corrections | 4/6/2023 | GARO TELMI |
| Plan Check Approved | 4/25/2023 | GARO TELMI |
| Issued | 4/25/2023 | APPLICANT |
| Permit Finaled | 3/12/2026 | DAVID BURKHEAD |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/23/2022 | STEVE MELGAR |
| Excavation more than 5-ft deep | Cleared | 6/23/2022 | CALOSHA APPROVED |
| Low Impact Development | Cleared | 7/20/2022 | ANDRES COVARRUBIAS |
| Construction near power lines | Cleared | 9/9/2022 | WALTER RAMIREZ |
| Historic Resource Verification | Cleared | 9/22/2022 | MAX LODER |
| Work Adjacent to Public Way | Cleared | 3/31/2023 | KHOUNG LE |
| Redevelopment Project Area | Cleared | 4/19/2023 | DAVID URITA |
| Site Plan review | Cleared | 4/19/2023 | POLONIA MAJAS |
| Specific Plan | Cleared | 4/19/2023 | POLONIA MAJAS |
| ZA Case | Cleared | 4/19/2023 | POLONIA MAJAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cefali,, David Allen; Lic. No.: S3658 | 4344 LAUREL CANYON BLVD_STE 3 STUDIO CITY, CA 91604 |
| Engineer | Queyrel,, David C.; Lic. No.: C42812 | 2153 TRAYNOR AVE PLACENTIA, CA 92633 |
| Engineer | Tang,, Stanley Siu Kei; Lic. No.: C56178 | 1105 N AVON STREET BURBANK, CA 91505 |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/26/2023 | Partial Approval | DAVID BURKHEAD |
| Deputy Grading | 4/27/2023 | Conditional Approval | RONALD JIMENEZ |
| Piling/Pier/Caisson | 4/27/2023 | Partial Approval | RONALD JIMENEZ |
| Deputy Grading | 4/28/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/1/2023 | Conditional Approval | RONALD JIMENEZ |
| Deputy Grading | 5/2/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Piling/Pier/Caisson | 5/2/2023 | Partial Inspection | GREGORY POMISH |
| Deputy Grading | 5/3/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/4/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/8/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/9/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/10/2023 | Approved | DAVID BURKHEAD |
| Excavation/Setback/Form/Re-Bar | 5/10/2023 | Partial Approval | DAVID BURKHEAD |
| Deputy Grading | 5/11/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/12/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/15/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/16/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/17/2023 | Partial Approval | EDWIN GREGORYONA |
| Excavation/Setback/Form/Re-Bar | 5/17/2023 | Partial Inspection | EDWIN GREGORYONA |
| Deputy Grading | 5/18/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/19/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Pre-Stress Concrete | 5/19/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/22/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 5/22/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 5/22/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/25/2023 | Approved | DAVID BURKHEAD |
| Deputy Pre-Stress Concrete | 5/25/2023 | Approved | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 5/25/2023 | Approved | DAVID BURKHEAD |
| Deputy Steel/Welding | 5/25/2023 | Approved | DAVID BURKHEAD |
| Excavation/Setback/Form/Re-Bar | 5/25/2023 | Partial Approval | DAVID BURKHEAD |
| Deputy Grading | 5/30/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 5/30/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 5/30/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/31/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 5/31/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 5/31/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 6/1/2023 | Conditional Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 6/1/2023 | Conditional Approval | GREGORY POMISH |
| Deputy Steel/Welding | 6/1/2023 | Conditional Approval | GREGORY POMISH |
| Excavation/Setback/Form/Re-Bar | 6/1/2023 | Partial Inspection | GREGORY POMISH |
| Deputy Grading | 6/2/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 6/2/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 6/2/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 6/5/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 6/5/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 6/5/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 6/7/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 6/7/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 6/7/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 6/9/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 6/9/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 6/9/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 6/13/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 6/14/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Excavation/Setback/Form/Re-Bar | 6/21/2023 | Partial Approval | TIMOTHY POWELL |
| Deputy Grading | 6/27/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 6/28/2023 | Conditional Approval | DAVID BURKHEAD |
| Excavation/Setback/Form/Re-Bar | 6/28/2023 | Partial Approval | DAVID BURKHEAD |
| Deputy Grading | 7/6/2023 | Conditional Approval | DAVID BURKHEAD |
| Excavation/Setback/Form/Re-Bar | 7/6/2023 | Partial Approval | DAVID BURKHEAD |
| Final | 7/28/2023 | Conditional Approval | DAVID BURKHEAD |
| Green Building Final | 7/28/2023 | Approved | DAVID BURKHEAD |
| Deputy Grading | 2/6/2024 | Conditional Approval | DAVID BURKHEAD |
| Deputy Grading | 2/9/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 2/20/2024 | Conditional Approval | DAVID BURKHEAD |
| Deputy Grading | 2/21/2024 | Conditional Approval | DAVID BURKHEAD |
| Deputy Grading | 2/22/2024 | Conditional Approval | DAVID BURKHEAD |
| Deputy Grading | 2/23/2024 | Conditional Approval | DAVID BURKHEAD |
| Deputy Grading | 2/27/2024 | Conditional Approval | DAVID BURKHEAD |
| Deputy Grading | 2/28/2024 | Conditional Approval | DAVID BURKHEAD |
| Deputy Grading | 2/29/2024 | Conditional Approval | DAVID BURKHEAD |
| Deputy Grading | 3/1/2024 | Conditional Approval | DAVID BURKHEAD |
| Deputy Grading | 4/25/2024 | Conditional Approval | DAVID BURKHEAD |
| Final | 3/5/2026 | Not Ready for Inspection | DAVID BURKHEAD |
| Final | 3/12/2026 | Permit Finaled | DAVID BURKHEAD |