1353 N WESTERN AVE 90027
Certificate Information: 1353 N WESTERN AVE 90027
- Application / Permit
- 22020-10000-00855
- Plan Check / Job No.
- B22LA06819
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- EARLY SHORING PERMIT FOR (N) MIXED-USE APARTMENT COMPLEX UNDER 21010-10000-00711
- Permit Issued
- Issued on 1/10/2023
- Issuing Office
- Metro
- Current Status
- Issued on 1/10/2023
Permit Application Status History
| Submitted | 4/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | ARMEN JIVALAGIAN |
| Corrections Issued | 5/17/2022 | ARMEN JIVALAGIAN |
| Quality Review Completed | 5/18/2022 | KEN GILL |
| Building Plans Picked Up | 5/20/2022 | APPLICANT |
| Plan Check Approved | 12/21/2022 | ARMEN JIVALAGIAN |
| Issued | 1/10/2023 | APPLICANT |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 5/23/2022 | DAVID URITA |
| Redevelopment Project Area | Cleared | 5/23/2022 | DAVID URITA |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2022 | WALLIE JONG |
| Excavation more than 5-ft deep | Cleared | 5/25/2022 | CALOSHA APPROVED |
| Density Bonus 12.22.A.31 | Cleared | 7/25/2022 | JAMES MCCARTHY |
| Opn space landscape/Water mgmt | Cleared | 8/1/2022 | ANNA VIDAL |
| Site Plan review | Cleared | 8/1/2022 | ANNA VIDAL |
| ZI | Cleared | 8/1/2022 | ANNA VIDAL |
| ZI | Cleared | 8/1/2022 | ANNA VIDAL |
| Hydrant and Access approval | Cleared | 8/3/2022 | KURT CORRAL |
| Building over 36-ft | Cleared | 8/4/2022 | CALOSHA APPROVED |
| Food establishment approval | Cleared | 8/4/2022 | LACDHS APPROVED |
| Address approval | Cleared | 8/8/2022 | STEVE MELGAR |
| Bicycle Parking | Cleared | 8/8/2022 | JEREMY CHOK |
| Highway dedication | Cleared | 8/8/2022 | STEVE MELGAR |
| Permit | Cleared | 8/8/2022 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 8/8/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 8/8/2022 | STEVE MELGAR |
| Driveway location | Cleared | 8/9/2022 | EDUARDO HERMOSO |
| Internal circulation | Cleared | 8/9/2022 | EDUARDO HERMOSO |
| Low Impact Development | Cleared | 8/9/2022 | JORGE MEJIA LEMUS |
| Trees in Parkway | Cleared | 8/17/2022 | ADALBERTO VERA |
| DAS Clearance | Cleared | 9/9/2022 | ARMEN JIVALAGIAN |
| Green Code | Cleared | 9/13/2022 | AARON COSTA |
| Fire Marshal Fire Life Safety | Cleared | 9/21/2022 | VIDAL GARCIA |
| Work Adjacent to Public Way | Cleared | 9/23/2022 | JOSE RODRIGUEZ |
| Encroachment in public way | Cleared | 9/28/2022 | JEREMY CHOK |
| Food Service Establishment | Cleared | 10/3/2022 | KENNETH BROWNE |
| Public Swimming Pool approval | Cleared | 10/18/2022 | LACDHS APPROVED |
Contact Information
| Contractor | Vcc Construction Corp; Lic. No.: 961705-B | P O BOX 2558 LITTLE ROCK, AR 72203 |
| Engineer | Benichou,, Ety; Lic. No.: S5263 | 888 S FIGUEROA ST 18TH FLOOR LOS ANGELES, CA 90017 |
| Engineer | Knur,, Reinard Thomas; Lic. No.: GE2755 | 1435 MONCADO DR GLENDALE, CA 91207 |
| Engineer | Krief,, Dan D; Lic. No.: C76041 | 6420 WILSHIRE BLVD STE 1000 LOS ANGELES, CA 90048 |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 1/23/2023 | Partial Approval | TIMOTHY POWELL |
| Pre-Inspection | 1/23/2023 | Approved | TIMOTHY POWELL |
| Deputy Steel/Welding | 1/25/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 1/26/2023 | Approved | TIMOTHY POWELL |
| Piling/Pier/Caisson | 1/26/2023 | Partial Inspection | TIMOTHY POWELL |
| Deputy Grading | 1/27/2023 | Conditional Approval | TIMOTHY POWELL |
| Piling/Pier/Caisson | 1/27/2023 | Partial Approval | TED RIES |
| Deputy Grading | 1/30/2023 | Conditional Approval | TIMOTHY POWELL |
| Deputy Grading | 1/31/2023 | Approved | TIMOTHY POWELL |
| Piling/Pier/Caisson | 1/31/2023 | Partial Inspection | TIMOTHY POWELL |
| Deputy Grading | 2/1/2023 | Conditional Approval | TIMOTHY POWELL |
| Deputy Grading | 2/3/2023 | Conditional Approval | TIMOTHY POWELL |
| Deputy Steel/Welding | 2/15/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 2/16/2023 | Conditional Approval | DAVID BURKHEAD |
| Deputy Steel/Welding | 2/16/2023 | Conditional Approval | DAVID BURKHEAD |
| Piling/Pier/Caisson | 2/16/2023 | Partial Inspection | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 2/17/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 2/17/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Other (see comments) | 2/22/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Other (see comments) | 2/28/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 3/7/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Piling/Pier/Caisson | 3/7/2023 | Partial Approval | TED RIES |
| Deputy Other (see comments) | 3/8/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 3/8/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Other (see comments) | 3/9/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Other (see comments) | 3/10/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Other (see comments) | 3/13/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 3/13/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 3/20/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Piling/Pier/Caisson | 3/20/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 3/24/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Piling/Pier/Caisson | 3/31/2023 | Partial Inspection | TIMOTHY POWELL |
| Deputy Grading | 4/11/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 4/13/2023 | Approved | TIMOTHY POWELL |
| Deputy Reinf. Concrete | 4/13/2023 | Approved | TIMOTHY POWELL |
| Piling/Pier/Caisson | 4/13/2023 | Partial Inspection | TIMOTHY POWELL |
| Deputy Grading | 4/14/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 4/14/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 4/18/2023 | Approved | RAMAZANALI ALMASI |
| Deputy Steel/Welding | 4/18/2023 | Approved | RAMAZANALI ALMASI |
| Piling/Pier/Caisson | 4/18/2023 | Approved | RAMAZANALI ALMASI |
| Deputy Steel/Welding | 4/26/2023 | Conditional Approval | DAVID BURKHEAD |
| Piling/Pier/Caisson | 4/26/2023 | Partial Inspection | DAVID BURKHEAD |
| Piling/Pier/Caisson | 5/9/2023 | Partial Approval | DAVID BURKHEAD |
| Deputy Steel/Welding | 5/16/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 7/13/2023 | Conditional Approval | DAVID BURKHEAD |
| Piling/Pier/Caisson | 7/13/2023 | Partial Inspection | DAVID BURKHEAD |
| Piling/Pier/Caisson | 7/20/2023 | Not Ready for Inspection | DAVID BURKHEAD |
| Piling/Pier/Caisson | 8/2/2023 | Not Ready for Inspection | DAVID BURKHEAD |
| Deputy Grading | 8/7/2023 | Conditional Approval | DAVID BURKHEAD |
| Deputy Steel/Welding | 8/11/2023 | Conditional Approval | DAVID BURKHEAD |
| Special/Order Compliance | 10/18/2023 | Approved | DAVID BURKHEAD |
| Excavation/Setback/Form/Re-Bar | 3/12/2024 | Not Ready for Inspection | DAVID BURKHEAD |