3530 S MOUNTAIN VIEW AVE 90066
Certificate Information: 3530 S MOUNTAIN VIEW AVE 90066
- Application / Permit
- 22020-10000-00535
- Plan Check / Job No.
- B22LA04166
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- RETAINING WALLS
- Permit Issued
- Issued on 7/14/2022
- Issuing Office
- Current Status
- Permit Finaled on 4/21/2025
Permit Application Status History
| Submitted | 3/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 3/25/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 3/30/2022 | KEN GILL |
| Building Plans Picked Up | 4/27/2022 | APPLICANT |
| Applicant returned to address corrections | 5/25/2022 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 7/12/2022 | MAHNAZ NOURHASHEMI |
| Issued | 7/14/2022 | APPLICANT |
| Permit Finaled | 4/18/2025 | JOHNNY MIRANDA |
Permit Application Clearance Information
| Work Adjacent to Public Way | Cleared | 5/6/2022 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 5/16/2022 | SAUL GARCIA |
| Grading Pre-Inspection | Cleared | 6/28/2022 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/11/2022 | Partial Approval | AL GAMBLE |
| Deputy Reinf. Concrete | 10/13/2022 | Approved | AL GAMBLE |
| Reinforced Masonry Frame | 11/8/2022 | Partial Inspection | AL GAMBLE |
| Reinforced Masonry Frame | 11/10/2022 | Partial Inspection | AL GAMBLE |
| Reinforced Masonry Frame | 11/17/2022 | Corrections Issued | AL GAMBLE |
| Reinforced Masonry Frame | 11/18/2022 | Partial Approval | AL GAMBLE |
| Masonry Wall/Backfill | 12/7/2022 | No Access for Inspection | AL GAMBLE |
| Masonry Wall/Backfill | 12/8/2022 | Partial Approval | AL GAMBLE |
| Deputy Reinf. Masonry | 12/28/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Reinf. Concrete | 1/30/2023 | Conditional Approval | RUSSELL BONVOULOIR |
| Excavation/Setback/Form/Re-Bar | 1/30/2023 | Not Ready for Inspection | MATTHEW JENKINS |
| Excavation/Setback/Form/Re-Bar | 2/1/2023 | Not Ready for Inspection | AL GAMBLE |
| Excavation/Setback/Form/Re-Bar | 2/3/2023 | Corrections Issued | MATTHEW JENKINS |
| Excavation/Setback/Form/Re-Bar | 2/9/2023 | Partial Approval | MATTHEW JENKINS |
| Masonry Wall/Backfill | 3/6/2023 | Partial Approval | MATTHEW JENKINS |
| Footing/Foundation/Slab | 10/23/2023 | Partial Approval | CHARLES POWELL |
| Masonry Wall/Backfill | 10/30/2023 | Corrections Issued | MATTHEW JENKINS |
| Deputy Reinf. Masonry | 11/2/2023 | Conditional Approval | MATTHEW JENKINS |
| Masonry Wall/Backfill | 11/2/2023 | Conditional Approval | MATTHEW JENKINS |
| Masonry Wall/Backfill | 11/14/2023 | Partial Approval | MATTHEW JENKINS |
| Deputy Reinf. Masonry | 11/30/2023 | Conditional Approval | MATTHEW JENKINS |
| Masonry Wall/Backfill | 12/19/2023 | Not Ready for Inspection | AL GAMBLE |
| Masonry Wall/Backfill | 12/27/2023 | Conditional Approval | MATTHEW JENKINS |
| Final | 4/16/2025 | Not Ready for Inspection | AL GAMBLE |
| Final | 4/18/2025 | Permit Finaled | JOHNNY MIRANDA |