375 N FORDYCE ROAD 90049

Certificate Information: 375 N FORDYCE ROAD 90049

Application / Permit
22020-10000-00486
Plan Check / Job No.
B22LA03743
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Shoring (Temporary)
Work Description
PROPOSED TEMPORARY SHORING FOR PROPOSED ADU/REC ROM. 2 of 3
Permit Issued
Issued on 2/28/2024
Issuing Office
Metro
Current Status
Issued on 2/28/2024

Permit Application Status History

Submitted 3/17/2022 APPLICANT
Assigned to Plan Check Engineer 3/24/2022 MICHAEL LOPEZ
Corrections Issued 3/31/2022 MICHAEL LOPEZ
Quality Review Completed 4/7/2022 SAI KHUM
Building Plans Picked Up 4/12/2022 APPLICANT
Applicant returned to address corrections 6/7/2022 MICHAEL LOPEZ
Applicant returned to address corrections 1/18/2023 MICHAEL LOPEZ
Applicant returned to address corrections 2/16/2023 MICHAEL LOPEZ
Applicant returned to address corrections 6/26/2023 MICHAEL LOPEZ
Plan Check Approved 6/28/2023 MICHAEL LOPEZ
Issued 2/28/2024 APPLICANT

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Hefner,, William Robert; Lic. No.: C17013 5820 WILSHIRE BLVD SUITE 500      LOS ANGELES, CA 90036
Contractor Abbott R T Construction Inc; Lic. No.: 746685-B 543 COUNTRY CLUB DRIVE BOX 205      SIMI VALLEY, CA 93065
Engineer Guo,, Dongfan; Lic. No.: C92889 668 N ATLANTIC BLVD UNIT B      ALHAMBRA, CA 91801
Engineer Liston,, Leonard Irvin; Lic. No.: C93123 889 PIERCE COURT, SUITE 101      THOUSAND OAKS, CA 91360
Engineer Ruan,, Federico R; Lic. No.: S6689 553 S OAK KNOLL AVE      PASADENA, CA 91101
Geologist Tsao,, Tze-Tzong; Lic. No.: EG1783 9428 ETON AVENUE #M      CHATSWORTH, CA 91311

Inspector Information

GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 9/26/2024 Approved VASIL MIHALEV
Deputy Grading 9/27/2024 Conditional Approval JOHNNY MIRANDA
Deputy Grading 10/1/2024 Conditional Approval JOHNNY MIRANDA
Pre-Inspection 10/1/2024 Not Ready for Inspection JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 10/2/2024 Partial Approval JOHNNY MIRANDA
Piling/Pier/Caisson 10/2/2024 Partial Approval JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 10/7/2024 Partial Approval JOHNNY MIRANDA
Piling/Pier/Caisson 10/7/2024 Partial Approval JOHNNY MIRANDA
Deputy Grading 10/9/2024 Conditional Approval JOHNNY MIRANDA
Deputy Grading 10/10/2024 Conditional Approval MATTHEW JENKINS
Deputy Grading 10/23/2024 Conditional Approval JOHNNY MIRANDA
Deputy Grading 10/24/2024 Conditional Approval JOHNNY MIRANDA
Deputy Grading 10/25/2024 Conditional Approval MATTHEW JENKINS
Deputy Grading 10/29/2024 No Access for Inspection VASIL MIHALEV
Excavation/Setback/Form/Re-Bar 11/4/2024 Partial Approval JOHNNY MIRANDA
Piling/Pier/Caisson 11/4/2024 Partial Approval JOHNNY MIRANDA
Deputy Reinf. Concrete 11/5/2024 Approved VASIL MIHALEV
Excavation/Setback/Form/Re-Bar 11/14/2024 Partial Approval MATTHEW JENKINS
Piling/Pier/Caisson 11/14/2024 Partial Inspection MATTHEW JENKINS
Excavation/Setback/Form/Re-Bar 12/2/2024 Partial Approval JOHNNY MIRANDA
Footing/Foundation/Slab 12/2/2024 Partial Approval JOHNNY MIRANDA
Piling/Pier/Caisson 12/2/2024 Partial Approval JOHNNY MIRANDA
Deputy Grading 12/3/2024 Approved VASIL MIHALEV
Deputy Grading 12/4/2024 Approved VASIL MIHALEV
Deputy Grading 12/5/2024 Approved VASIL MIHALEV
Deputy Grading 12/6/2024 Conditional Approval JOHNNY MIRANDA
Deputy Grading 12/9/2024 Approved VASIL MIHALEV
Excavation/Setback/Form/Re-Bar 12/10/2024 Approved VASIL MIHALEV
Piling/Pier/Caisson 12/10/2024 Approved VASIL MIHALEV
Excavation/Setback/Form/Re-Bar 12/16/2024 Not Ready for Inspection JOHNNY MIRANDA
Piling/Pier/Caisson 12/16/2024 Not Ready for Inspection JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 12/17/2024 Partial Approval JOHNNY MIRANDA
Piling/Pier/Caisson 12/17/2024 Partial Approval JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 1/6/2025 Partial Approval MATTHEW JENKINS
Piling/Pier/Caisson 1/6/2025 Partial Inspection MATTHEW JENKINS
Deputy Reinf. Concrete 1/7/2025 Conditional Approval MATTHEW JENKINS
Deputy Reinf. Concrete 1/13/2025 No Access for Inspection VASIL MIHALEV
Excavation/Setback/Form/Re-Bar 1/30/2025 Partial Approval MATTHEW JENKINS
Piling/Pier/Caisson 1/30/2025 Partial Inspection MATTHEW JENKINS
Excavation/Setback/Form/Re-Bar 2/3/2025 Partial Approval MATTHEW JENKINS
Piling/Pier/Caisson 2/3/2025 Partial Inspection MATTHEW JENKINS
Piling/Pier/Caisson 2/25/2025 Partial Approval MATTHEW JENKINS
Deputy Grading 2/27/2025 Conditional Approval MATTHEW JENKINS
Deputy Reinf. Concrete 3/3/2025 Conditional Approval MATTHEW JENKINS
Excavation/Setback/Form/Re-Bar 3/4/2025 Partial Approval MATTHEW JENKINS
Piling/Pier/Caisson 3/4/2025 Partial Inspection MATTHEW JENKINS
Piling/Pier/Caisson 3/18/2025 Partial Approval JOHNNY MIRANDA
Piling/Pier/Caisson 3/20/2025 Not Ready for Inspection MATTHEW JENKINS
Piling/Pier/Caisson 3/21/2025 Partial Inspection MATTHEW JENKINS
Excavation/Setback/Form/Re-Bar 4/11/2025 Approved LANNY MERRICK
Piling/Pier/Caisson 4/11/2025 Approved LANNY MERRICK
Deputy Grading 4/29/2025 Conditional Approval JOHNNY MIRANDA
Piling/Pier/Caisson 7/17/2025 Partial Inspection MATTHEW JENKINS
Piling/Pier/Caisson 7/18/2025 Not Ready for Inspection MATTHEW JENKINS
Grading Pre-Inspection 7/30/2025 Partial Inspection MATTHEW JENKINS
Excavation/Setback/Form/Re-Bar 1/27/2026 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA