1021 N VERMONT AVE 90029
Certificate Information: 1021 N VERMONT AVE 90029
- Application / Permit
- 22020-10000-00202
- Plan Check / Job No.
- B22LA01328
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- Temporary shoring for basement construction
- Permit Issued
- Issued on 3/10/2022
- Issuing Office
- Current Status
- Permit Finaled on 2/5/2025
Permit Application Status History
| Submitted | 1/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2022 | VU NGUYEN |
| Corrections Issued | 1/27/2022 | VU NGUYEN |
| Plan Check Approved | 3/10/2022 | VU NGUYEN |
| Issued | 3/10/2022 | APPLICANT |
| Permit Finaled | 2/4/2025 | DAVID BURKHEAD |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2022 | STEVE MELGAR |
| Excavation more than 5-ft deep | Cleared | 2/3/2022 | CALOSHA APPROVED |
| Metro Rail approval | Cleared | 2/4/2022 | VU NGUYEN |
| Miscellaneous | Cleared | 2/4/2022 | MAXFIELD VERMY |
| Miscellaneous | Cleared | 2/4/2022 | MAXFIELD VERMY |
| Miscellaneous | Cleared | 2/4/2022 | MAXFIELD VERMY |
| Miscellaneous | Cleared | 2/4/2022 | MAXFIELD VERMY |
| Miscellaneous | Cleared | 2/4/2022 | MAXFIELD VERMY |
| Miscellaneous | Cleared | 2/4/2022 | MAXFIELD VERMY |
| Specific Plan | Cleared | 2/4/2022 | MAXFIELD VERMY |
| Work Adjacent to Public Way | Cleared | 2/4/2022 | JOSE RODRIGUEZ |
| ZI | Cleared | 2/4/2022 | MAXFIELD VERMY |
Contact Information
| Contractor | Walton Construction Inc; Lic. No.: 1034491-B | 358 E FOOTHILL BLVD STE 100 SAN DIMAS, CA 91773 |
| Engineer | Funk,, David Lyle; Lic. No.: S5421 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/30/2022 | Corrections Issued | SORIN CIRSTOIU |
| Excavation/Setback/Form/Re-Bar | 5/4/2022 | Not Ready for Inspection | JONATHAN QUACH |
| Deputy Reinf. Concrete | 7/8/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 7/11/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 7/12/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 7/13/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 7/14/2022 | Conditional Approval | TED RIES |
| Final | 2/4/2025 | Permit Finaled | DAVID BURKHEAD |