936 S FEDORA ST 1-30 90006

Certificate Information: 936 S FEDORA ST 1-30 90006

Application / Permit
22020-10000-00073
Plan Check / Job No.
B21LA11458
Group
Building
Type
Nonbldg-New
Sub-Type
Apartment
Primary Use
(23) Shoring (Temporary)
Work Description
Temporary Shoring for construction of an apartment
Permit Issued
Issued on 3/17/2023
Issuing Office
Metro
Current Status
Issued on 3/17/2023

Permit Application Status History

Submitted 12/4/2021 APPLICANT
Assigned to Plan Check Engineer 12/29/2021 VU NGUYEN
Corrections Issued 1/13/2022 VU NGUYEN
Quality Review Completed 1/18/2022 EUGENE BARBEAU
Applicant returned to address corrections 2/25/2022 VU NGUYEN
Applicant returned to address corrections 4/21/2022 VU NGUYEN
Applicant returned to address corrections 4/27/2022 VU NGUYEN
Plan Check Approved 3/1/2023 VU NGUYEN
Issued 3/17/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/14/2022 CHRISTOPHER ROCHA
Excavation more than 5-ft deep Cleared 3/3/2022 CALOSHA APPROVED
Work Adjacent to Public Way Cleared 5/6/2022 KHOUNG LE
Historic Resource Verification Cleared 5/26/2022 DAVID URITA
Miscellaneous Cleared 5/26/2022 DANIEL CORONADO
Miscellaneous Cleared 5/26/2022 DANIEL CORONADO
Miscellaneous Cleared 5/26/2022 DANIEL CORONADO
Miscellaneous Cleared 5/26/2022 DANIEL CORONADO
ZA Case Cleared 5/26/2022 DANIEL CORONADO
Redevelopment Project Area Cleared 8/31/2022 DAVID URITA
Miscellaneous Cleared 9/6/2022 DANIEL CORONADO

Contact Information

Contractor Siglo Design & Construction Llc; Lic. No.: 1100710-B 611 WILSHIRE BLVD   SUITE 1416    LOS ANGELES, CA 90017
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Engineer Xia,, Ji; Lic. No.: C89014 260 S LOS ROBLES AVE, STE 100      PASADENA, CA 91101

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 9/8/2023 Conditional Approval NICK DANERI
Grading Pre-Inspection 9/11/2023 Partial Inspection NICK DANERI
Pre-Inspection 9/11/2023 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 10/13/2023 No Access for Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 11/8/2023 Not Ready for Inspection NICK DANERI
Final 4/5/2024 Not Ready for Inspection NICK DANERI