1430 W 9TH ST 90732

Certificate Information: 1430 W 9TH ST 90732

Application / Permit
22019-10000-02245
Plan Check / Job No.
B22LA08921
Group
Building
Type
Bldg-Demolition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Demolish existing single family house and detached garage "clear lot" dpi under: 22019-10000-02553 mail sent on: 05/31/2022 building more than 45 years old
Permit Issued
Issued on 1/19/2024
Issuing Office
Metro
Current Status
Permit Finaled on 3/27/2024

Permit Application Status History

Submitted 5/11/2022 APPLICANT
Assigned to Plan Check Engineer 5/12/2022 SUNMIN LEE
Corrections Issued 5/13/2022 SUNMIN LEE
Applicant returned to address corrections 5/24/2022 SUNMIN LEE
Applicant returned to address corrections 7/5/2022 SUNMIN LEE
Plan Check Approved 7/7/2022 SUNMIN LEE
No Progress 1/19/2024 SUNMIN LEE
Plan Check Approved 1/19/2024 SUNMIN LEE
Plan Check Approved 1/19/2024 SUNMIN LEE
Plan Check Approved 1/19/2024 SUNMIN LEE
Issued 1/19/2024 APPLICANT
Permit Finaled 3/27/2024 WILLIAM ROSE

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Precision General Construction Inc; Lic. No.: 1030555-B 1323 W MALBORO AVENUE      ANAHEIM, CA 92801

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Final 2/14/2024 Corrections Issued ANSON MAGLASANG
Protection Fence/Barricades 2/14/2024 Approved ANSON MAGLASANG
Final 3/5/2024 Not Ready for Inspection JAMES CHAVEZ
Sewer Cap 3/5/2024 Not Ready for Inspection JAMES CHAVEZ
Final 3/27/2024 Permit Finaled WILLIAM ROSE
Sewer Cap 3/27/2024 Approved WILLIAM ROSE