528 W 20TH ST 90731

Certificate Information: 528 W 20TH ST 90731

Application / Permit
22016-40000-34653
Plan Check / Job No.
B22SP00070
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 1-STORY LAUNDRY/STORAGE ROOM INTO ACCESSORY DWELLING UNIT (ADU) PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 10/12/2023
Issuing Office
San Pedro
Current Status
CofO Issued on 4/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2022 APPLICANT
Assigned to Plan Check Engineer 11/15/2022 LAWRENCE QUIRANTE
Corrections Issued 11/22/2022 LAWRENCE QUIRANTE
Applicant returned to address corrections 3/14/2023 LAWRENCE QUIRANTE
Applicant returned to address corrections 9/28/2023 SERGIO SILVA
Plan Check Approved 10/5/2023 SERGIO SILVA
Issued 10/12/2023 APPLICANT
CofO in Progress 4/8/2025 JOSEPH MCGARRY
CofO Issued 4/9/2025 ANSON MAGLASANG
Permit Finaled 4/9/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 9/12/2023 KHAING AYE
Eng Process Fee Ord 176,300 Cleared 9/12/2023 KHAING AYE
Sewer availability Cleared 9/12/2023 KHAING AYE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/28/2024 Corrections Issued JAMES CHAVEZ
Underground Mechanical 3/28/2024 Corrections Issued JAMES CHAVEZ
Underground Mechanical 4/1/2024 Corrections Issued ANSON MAGLASANG
PLUMBING-Rough 5/9/2024 Partial Approval JAMES CHAVEZ
Excavation/Setback/Form/Re-Bar 5/16/2024 Corrections Issued JAMES CHAVEZ
Footing/Foundation/Slab 6/7/2024 Corrections Issued EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 6/14/2024 Approved JAMES CHAVEZ
Footing/Foundation/Slab 6/14/2024 Approved JAMES CHAVEZ
Drywall Nailing 6/25/2024 Not Ready for Inspection JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 6/25/2024 Partial Approval JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 6/28/2024 Partial Approval JAMES CHAVEZ
ELECTRICAL-Rough 7/10/2024 Corrections Issued JAMES CHAVEZ
PLUMBING-Rough 7/10/2024 Corrections Issued JAMES CHAVEZ
ELECTRICAL-Rough 7/15/2024 Corrections Issued JAMES CHAVEZ
Interior/Exterior Lathing 7/15/2024 Partial Approval JAMES CHAVEZ
PLUMBING-Rough 7/15/2024 Approved JAMES CHAVEZ
ELECTRICAL-Rough 7/17/2024 Approved JAMES CHAVEZ
HVAC-Rough 7/17/2024 Corrections Issued JAMES CHAVEZ
HVAC-Rough 7/22/2024 Corrections Issued ANSON MAGLASANG
BUILDING-Rough-Frame 7/24/2024 Not Ready for Inspection JAMES CHAVEZ
HVAC-Rough 7/24/2024 Not Ready for Inspection JAMES CHAVEZ
BUILDING-Rough-Frame 7/25/2024 Approved EUGENE CASSIDY
HVAC-Rough 7/25/2024 Approved EUGENE CASSIDY
Insulation 7/30/2024 Corrections Issued JOSEPH MCGARRY
Insulation 8/26/2024 Not Ready for Inspection ANSON MAGLASANG
Insulation 8/30/2024 Approved EUGENE CASSIDY
Drywall Nailing 9/16/2024 Approved JOSEPH MCGARRY
Shower Pan 10/11/2024 Corrections Issued EUGENE CASSIDY
Shower Pan 10/21/2024 Corrections Issued JOSEPH MCGARRY
Interior/Exterior Lathing 10/23/2024 Approved JOSEPH MCGARRY
Shower Pan 10/23/2024 Approved JOSEPH MCGARRY
Gas Test 11/26/2024 Corrections Issued JOSEPH MCGARRY
Gas Test 12/5/2024 Approved BEN MOLSTAD
Service/Power Release 1/28/2025 Corrections Issued ANSON MAGLASANG
ELECTRICAL-Final 2/10/2025 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Final 2/13/2025 Approved JOSEPH MCGARRY
Service/Power Release 2/13/2025 Not Ready for Inspection JOSEPH MCGARRY
Final 3/24/2025 Corrections Issued JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 3/24/2025 SGSOV Not Ready JOSEPH MCGARRY
Smoke Detectors 3/24/2025 Approved JOSEPH MCGARRY
Final 4/2/2025 OK to Issue CofO JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 4/2/2025 SGSOV Approved JOSEPH MCGARRY