528 W 20TH ST 90731
Certificate Information: 528 W 20TH ST 90731
- Application / Permit
- 22016-40000-34653
- Plan Check / Job No.
- B22SP00070
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 1-STORY LAUNDRY/STORAGE ROOM INTO ACCESSORY DWELLING UNIT (ADU) PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 10/12/2023
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 4/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/15/2022 | LAWRENCE QUIRANTE |
| Corrections Issued | 11/22/2022 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 3/14/2023 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 9/28/2023 | SERGIO SILVA |
| Plan Check Approved | 10/5/2023 | SERGIO SILVA |
| Issued | 10/12/2023 | APPLICANT |
| CofO in Progress | 4/8/2025 | JOSEPH MCGARRY |
| CofO Issued | 4/9/2025 | ANSON MAGLASANG |
| Permit Finaled | 4/9/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 9/12/2023 | KHAING AYE |
| Eng Process Fee Ord 176,300 | Cleared | 9/12/2023 | KHAING AYE |
| Sewer availability | Cleared | 9/12/2023 | KHAING AYE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/28/2024 | Corrections Issued | JAMES CHAVEZ |
| Underground Mechanical | 3/28/2024 | Corrections Issued | JAMES CHAVEZ |
| Underground Mechanical | 4/1/2024 | Corrections Issued | ANSON MAGLASANG |
| PLUMBING-Rough | 5/9/2024 | Partial Approval | JAMES CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 5/16/2024 | Corrections Issued | JAMES CHAVEZ |
| Footing/Foundation/Slab | 6/7/2024 | Corrections Issued | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 6/14/2024 | Approved | JAMES CHAVEZ |
| Footing/Foundation/Slab | 6/14/2024 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 6/25/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2024 | Partial Approval | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2024 | Partial Approval | JAMES CHAVEZ |
| ELECTRICAL-Rough | 7/10/2024 | Corrections Issued | JAMES CHAVEZ |
| PLUMBING-Rough | 7/10/2024 | Corrections Issued | JAMES CHAVEZ |
| ELECTRICAL-Rough | 7/15/2024 | Corrections Issued | JAMES CHAVEZ |
| Interior/Exterior Lathing | 7/15/2024 | Partial Approval | JAMES CHAVEZ |
| PLUMBING-Rough | 7/15/2024 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Rough | 7/17/2024 | Approved | JAMES CHAVEZ |
| HVAC-Rough | 7/17/2024 | Corrections Issued | JAMES CHAVEZ |
| HVAC-Rough | 7/22/2024 | Corrections Issued | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 7/24/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| HVAC-Rough | 7/24/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 7/25/2024 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 7/25/2024 | Approved | EUGENE CASSIDY |
| Insulation | 7/30/2024 | Corrections Issued | JOSEPH MCGARRY |
| Insulation | 8/26/2024 | Not Ready for Inspection | ANSON MAGLASANG |
| Insulation | 8/30/2024 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 9/16/2024 | Approved | JOSEPH MCGARRY |
| Shower Pan | 10/11/2024 | Corrections Issued | EUGENE CASSIDY |
| Shower Pan | 10/21/2024 | Corrections Issued | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 10/23/2024 | Approved | JOSEPH MCGARRY |
| Shower Pan | 10/23/2024 | Approved | JOSEPH MCGARRY |
| Gas Test | 11/26/2024 | Corrections Issued | JOSEPH MCGARRY |
| Gas Test | 12/5/2024 | Approved | BEN MOLSTAD |
| Service/Power Release | 1/28/2025 | Corrections Issued | ANSON MAGLASANG |
| ELECTRICAL-Final | 2/10/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Final | 2/13/2025 | Approved | JOSEPH MCGARRY |
| Service/Power Release | 2/13/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| Final | 3/24/2025 | Corrections Issued | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 3/24/2025 | SGSOV Not Ready | JOSEPH MCGARRY |
| Smoke Detectors | 3/24/2025 | Approved | JOSEPH MCGARRY |
| Final | 4/2/2025 | OK to Issue CofO | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 4/2/2025 | SGSOV Approved | JOSEPH MCGARRY |