4818 1/2 S BELOIT AVE 90230
Certificate Information: 4818 1/2 S BELOIT AVE 90230
- Application / Permit
- 22016-30001-13663
- Plan Check / Job No.
- B24WL07500
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- supplemental ref to pcis # 22016-30000-13663, to change work description to new ADU per ...
- Permit Issued
- Issued on 12/10/2024
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 4/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2024 | ZENA HADDIS |
| Corrections Issued | 10/2/2024 | ZENA HADDIS |
| Quality Review Completed | 10/2/2024 | KAVIAN REFAHI |
| Building Plans Picked Up | 10/3/2024 | APPLICANT |
| Plan Check Approved | 12/10/2024 | ZENA HADDIS |
| Issued | 12/10/2024 | APPLICANT |
| Permit Finaled | 4/25/2025 | BOBBY KEY |
Permit Application Clearance Information
| Specific Plan | Cleared | 11/14/2024 | JOSHUA JONES |
| Roof/Waste drainage to street | Cleared | 11/19/2024 | DIANA RENTERIA |
| Sewer availability | Cleared | 11/19/2024 | DIANA RENTERIA |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2024 | DIANA RENTERIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chen,, Jong; Lic. No.: C55404 | 9646 GARVEY AVE STE 206 SOUTH EL MONTE, CA 91733 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/31/2025 | Partial Approval | MICHAEL ALLEN |
| Excavation/Setback/Form/Re-Bar | 2/4/2025 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 2/4/2025 | Approved | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2025 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2025 | Partial Approval | MICHAEL ALLEN |
| Green Building Rough | 3/14/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| ELECTRICAL-Rough | 4/1/2025 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 4/1/2025 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 4/1/2025 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 4/10/2025 | Approved | MICHAEL ALLEN |
| Gas Test | 4/10/2025 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 4/10/2025 | Partial Approval | MICHAEL ALLEN |
| Interior/Exterior Lathing | 4/10/2025 | Partial Approval | MICHAEL ALLEN |
| PLUMBING-Rough | 4/10/2025 | Partial Approval | MICHAEL ALLEN |
| Special/Order Compliance | 4/10/2025 | Corrections Issued | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 4/16/2025 | Approved | MICHAEL ALLEN |
| Green Building Rough | 4/16/2025 | Approved | MICHAEL ALLEN |
| Special/Order Compliance | 4/16/2025 | Corrections Issued | MICHAEL ALLEN |