112 N WINDSOR BLVD 90004
Certificate Information: 112 N WINDSOR BLVD 90004
- Application / Permit
- 22016-30000-39298
- Plan Check / Job No.
- B22WL04711
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert an (E) detached garage to ADU and storage in the rear of the lot per CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 8/1/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2023 | RICHARD GARCIA |
| Corrections Issued | 1/10/2023 | RICHARD GARCIA |
| Building Plans Picked Up | 1/30/2023 | APPLICANT |
| Applicant returned to address corrections | 4/10/2023 | JOHNPAUL ISIP |
| Plan Check Approved | 6/23/2023 | RICHARD GARCIA |
| Plan Check Approved | 6/23/2023 | JAHANSHAH POURHASSAN |
| Issued | 8/1/2023 | APPLICANT |
| CofO in Progress | 8/2/2024 | JEFFREY MEAD |
| Permit Finaled | 9/6/2024 | RUBEN SALAS |
| CofO Issued | 9/6/2024 | RUBEN SALAS |
| Permit Finaled | 9/6/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/15/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 3/15/2023 | TREVOR QUAN |
| HPOZ | Cleared | 3/20/2023 | DAMIAN GATTO |
| ZI | Cleared | 3/20/2023 | DAMIAN GATTO |
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2023 | ANA SORIANO |
| Construction within easement | Cleared | 6/6/2023 | RIDWAN HARDY |
Contact Information
| Architect | Nichols,, Mark; Lic. No.: C38099 | 3964-1/2 BEETHOVEN STREET LOS ANGELES, CA 90066 |
| Contractor | Castillo Construction Services Inc; Lic. No.: 1076756-B | 5617 LEXINGTON AVE APT 1 LOS ANGELES, CA 91106 |
| Engineer | Daoud,, Richard A; Lic. No.: S6585 | 714 W OLYMPIC BLVD STE 617 LOS ANGELES, CA 90015 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/14/2023 | Partial Inspection | SCOTT FINNILA |
| PLUMBING-Rough | 8/17/2023 | Approved | ROY SPAULDING |
| Footing/Foundation/Slab | 8/22/2023 | Conditional Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 10/13/2023 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 10/13/2023 | Corrections Issued | JEFFREY MEAD |
| Green Building Rough | 10/13/2023 | Not Ready for Inspection | JEFFREY MEAD |
| HVAC-Rough | 10/13/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 10/13/2023 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 10/30/2023 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 10/30/2023 | Approved | JEFFREY MEAD |
| HVAC-Rough | 10/30/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 10/30/2023 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 10/31/2023 | Partial Approval | JEFFREY MEAD |
| Insulation | 11/3/2023 | Corrections Issued | JEFFREY MEAD |
| Wood Frame | 11/3/2023 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 11/6/2023 | Conditional Approval | JEFFREY MEAD |
| Insulation | 11/6/2023 | Approved | JEFFREY MEAD |
| Drywall Nailing | 11/7/2023 | Approved | JEFFREY MEAD |
| Green Building Rough | 11/7/2023 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 11/7/2023 | Approved | JEFFREY MEAD |
| Sewer | 12/11/2023 | Partial Approval | JEFFREY MEAD |
| PLUMBING-Rough | 12/26/2023 | Corrections Issued | JEFFREY MEAD |
| Underground Mechanical | 1/4/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Underground Mechanical | 1/10/2024 | Corrections Issued | JEFFREY MEAD |
| Underground Mechanical | 1/31/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Underground Mechanical | 2/21/2024 | No Access for Inspection | JEFFREY MEAD |
| Underground Mechanical | 2/28/2024 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 4/17/2024 | Approved | ENRIQUE MIRELES |
| Final | 4/17/2024 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 4/17/2024 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 4/17/2024 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 4/17/2024 | Approved | ENRIQUE MIRELES |
| Final | 8/1/2024 | OK to Issue CofO | JEFFREY MEAD |