7912-7914 N CAPISTRANO AVE 91304

Certificate Information: 7912-7914 N CAPISTRANO AVE 91304

Application / Permit
22016-30000-38973
Plan Check / Job No.
B22WL04647
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
convert existing 2-car garage to ADU per state law.
Permit Issued
Issued on 2/9/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2022 APPLICANT
Assigned to Plan Check Engineer 12/27/2022 KAVIAN REFAHI
Corrections Issued 12/27/2022 KAVIAN REFAHI
Plan Check Approved 1/27/2023 KAVIAN REFAHI
Issued 2/9/2023 APPLICANT
CofO in Progress 2/12/2024 JEFFREY HARTLINE
Permit Finaled 2/27/2024 JOHN JANSON
CofO Issued 2/27/2024 JOHN JANSON
Permit Finaled 2/27/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/12/2023 CHRIS CHAHBAZ
Sewer availability Cleared 1/12/2023 CHRIS CHAHBAZ
Eng Process Fee Ord 176,300 Cleared 1/18/2023 CHRIS CHAHBAZ

Contact Information

Contractor Bakhtiyari Tooraj; Lic. No.: 922493-B 23300 COHASSET STREET      WEST HILLS, CA 91304

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/2/2023 Conditional Approval KRISTEN CAUSEY
Sewer 3/2/2023 Approved KRISTEN CAUSEY
ELECTRICAL-Rough 4/7/2023 Approved KRISTEN CAUSEY
PLUMBING-Rough 4/7/2023 Corrections Issued KRISTEN CAUSEY
Wood Frame 4/7/2023 Not Ready for Inspection KRISTEN CAUSEY
Interior/Exterior Lathing 4/11/2023 Not Ready for Inspection KRISTEN CAUSEY
PLUMBING-Rough 4/11/2023 Approved KRISTEN CAUSEY
Shower Pan 4/11/2023 Approved KRISTEN CAUSEY
Special/Order Compliance 4/11/2023 Approved HORACE FULTZ
Wood Frame 4/11/2023 Partial Inspection KRISTEN CAUSEY
HVAC-Rough 4/18/2023 Corrections Issued CHRIS CHRISTENSEN
Interior/Exterior Lathing 4/18/2023 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 4/18/2023 Approved CHRIS CHRISTENSEN
Shower Pan 4/18/2023 Approved CHRIS CHRISTENSEN
Wood Frame 4/18/2023 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 4/24/2023 SGSOV Not Ready CHRIS CHRISTENSEN
Insulation 4/27/2023 Not Ready for Inspection KRISTEN CAUSEY
Drywall Nailing 5/4/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Drywall Nailing 5/9/2023 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 7/19/2023 SGSOV Not Ready CHRIS CHRISTENSEN
BUILDING-Rough-Frame 1/8/2024 Approved JEFFREY HARTLINE
Final 1/8/2024 Corrections Issued JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 1/8/2024 SGSOV Approved JEFFREY HARTLINE
Smoke Detectors 1/8/2024 Approved JEFFREY HARTLINE
Final 1/10/2024 Partial Approval JEFFREY HARTLINE
Special/Order Compliance 1/11/2024 Corrections Issued JEFFREY HARTLINE
Service/Power Release 2/8/2024 Approved JEFFREY HARTLINE
Final 2/12/2024 OK to Issue CofO JEFFREY HARTLINE