617 E 116TH ST 90059
Certificate Information: 617 E 116TH ST 90059
- Application / Permit
- 22016-30000-38824
- Plan Check / Job No.
- B22WL04637
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Detached garage and laundry room conversion to Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 12/6/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 8/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2023 | JASON JANGADA |
| Corrections Issued | 1/10/2023 | JASON JANGADA |
| Building Plans Picked Up | 1/20/2023 | APPLICANT |
| Applicant returned to address corrections | 2/8/2023 | AMY GUEVARRA |
| Applicant returned to address corrections | 3/8/2023 | RICHARD GARCIA |
| Plan Check Approved | 12/6/2023 | EDWIN ESPIN |
| Issued | 12/6/2023 | APPLICANT |
| CofO in Progress | 8/8/2025 | ANTHONY EGSON |
| Permit Finaled | 8/8/2025 | ANSON MAGLASANG |
| CofO Issued | 8/8/2025 | ANSON MAGLASANG |
| Permit Finaled | 8/8/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 2/16/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 2/16/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2023 | TREVOR QUAN |
| Construction near power lines | Cleared | 6/6/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gamage,, Sarath Kankanam; Lic. No.: C60552 | 18316 GLENBURN AVENUE TORRANCE, CA 90504 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/11/2024 | Corrections Issued | BEN MOLSTAD |
| Gas Test | 3/13/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 3/13/2024 | Partial Approval | BEN MOLSTAD |
| Deputy Drilled-In Anchors | 3/20/2024 | Conditional Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 3/22/2024 | Approved | BEN MOLSTAD |
| Reinforced Concrete Frame | 3/22/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 4/23/2024 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Rough | 4/25/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 4/29/2024 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 4/29/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 5/7/2024 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 5/8/2024 | Corrections Issued | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2024 | Partial Approval | BEN MOLSTAD |
| Green Building Rough | 5/8/2024 | Not Ready for Inspection | BEN MOLSTAD |
| MERV13>=Rough | 5/8/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Wood Frame | 5/8/2024 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 5/13/2024 | No Access for Inspection | BEN MOLSTAD |
| Deputy Wood Construction | 5/13/2024 | No Access for Inspection | BEN MOLSTAD |
| Green Building Rough | 5/13/2024 | No Access for Inspection | BEN MOLSTAD |
| MERV13>=Rough | 5/13/2024 | No Access for Inspection | BEN MOLSTAD |
| Wood Frame | 5/13/2024 | No Access for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2024 | Partial Approval | JAMES CHAVEZ |
| HVAC-Rough | 5/15/2024 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 5/17/2024 | Approved | BEN MOLSTAD |
| Green Building Rough | 5/17/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 5/17/2024 | Partial Approval | BEN MOLSTAD |
| MERV13>=Rough | 5/17/2024 | Approved | BEN MOLSTAD |
| Insulation | 5/30/2024 | Approved | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2024 | Approved | BEN MOLSTAD |
| Deputy Wood Construction | 6/6/2024 | Conditional Approval | BEN MOLSTAD |
| Drywall Nailing | 6/17/2024 | Approved | BEN MOLSTAD |
| Shower Pan | 6/17/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 6/27/2024 | Approved | BEN MOLSTAD |
| Shower Pan | 6/27/2024 | Approved | BEN MOLSTAD |
| Final | 12/19/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 12/19/2024 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 12/19/2024 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 12/19/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 5/1/2025 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 7/22/2025 | Corrections Issued | ANTHONY EGSON |
| Final | 7/22/2025 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 7/22/2025 | Approved | ANTHONY EGSON |
| HVAC-Final | 7/22/2025 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 7/22/2025 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 7/22/2025 | SGSOV Not Ready | ANTHONY EGSON |
| ELECTRICAL-Final | 8/6/2025 | Approved | ANTHONY EGSON |
| Final | 8/6/2025 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 8/6/2025 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 8/6/2025 | SGSOV Approved | ANTHONY EGSON |
| Final | 8/8/2025 | OK to Issue CofO | ANTHONY EGSON |