12035 W MARINE ST 90066

Certificate Information: 12035 W MARINE ST 90066

Application / Permit
22016-30000-38633
Plan Check / Job No.
B22WL04610
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1st & 2nd floor remodel of (e) 2-story S.F.D., all windows & doors are replaced, no change in floor area per engineer's calc. new trellis addition to the front and rear of SFD
Permit Issued
Issued on 4/8/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/21/2022 APPLICANT
Assigned to Plan Check Engineer 1/7/2023 ALFREDO JARA
Building Plans Picked Up 1/13/2023 APPLICANT
Corrections Issued 1/17/2023 ALFREDO JARA
Applicant returned to address corrections 3/30/2023 AMY GUEVARRA
Applicant returned to address corrections 4/4/2023 DAVID CASTILLO
Plan Check Approved 4/24/2023 AMY GUEVARRA
Plan Check Approved 4/1/2025 JOHNPAUL ISIP
Issued 4/8/2025 APPLICANT
CofO in Progress 10/1/2025 KIRK SANDERS
Permit Finaled 10/7/2025 RICHARD STEINBACH
CofO Issued 10/7/2025 RICHARD STEINBACH
Permit Finaled 10/7/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/22/2023 JASON NG
Roof/Waste drainage to street Cleared 3/22/2023 JASON NG
Grading Pre-Inspection Cleared 3/30/2023 ALFREDO JARA

Contact Information

Architect , ; Lic. No.: C34881 315 WASHINGTON BLVD   SUITE 2    VENICE BEACH, CA 90292
Contractor Ludwig S C Construction Llc; Lic. No.: 991853-B 3969 ALLA RD      LOS ANGELES, CA 90066
Engineer Galbreath,, Sean; Lic. No.: S5653 600 SOUTH LAKE AVE STE 308      PASADENA, CA 91106

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/13/2025 Approved WILBER ROSALES
Footing/Foundation/Slab 5/13/2025 Approved WILBER ROSALES
ELECTRICAL-Rough 5/23/2025 Approved WILBER ROSALES
PLUMBING-Rough 5/23/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 5/28/2025 Corrections Issued WILBER ROSALES
Deputy Wood Construction 5/28/2025 Conditional Approval WILBER ROSALES
HVAC-Rough 5/28/2025 Approved WILBER ROSALES
Drywall Nailing 6/3/2025 Approved WILBER ROSALES
Insulation 6/3/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 6/9/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 9/17/2025 Approved KIRK SANDERS
Final 9/17/2025 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 9/17/2025 SGSOV Approved KIRK SANDERS
Smoke Detectors 9/17/2025 Partial Approval KIRK SANDERS
Final 9/30/2025 OK to Issue CofO KIRK SANDERS
Smoke Detectors 9/30/2025 Approved KIRK SANDERS