12015 W HAVELOCK AVE 90230
Certificate Information: 12015 W HAVELOCK AVE 90230
- Application / Permit
- 22016-30000-37564
- Plan Check / Job No.
- B22WL04506
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of garage to ADU per WFPP.
- Permit Issued
- Issued on 7/25/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/21/2022 | RICHARD GARCIA |
| Corrections Issued | 12/21/2022 | RICHARD GARCIA |
| Building Plans Picked Up | 1/6/2023 | APPLICANT |
| Applicant returned to address corrections | 3/30/2023 | RICHARD GARCIA |
| Applicant returned to address corrections | 5/9/2023 | RICHARD GARCIA |
| Applicant returned to address corrections | 6/6/2023 | RICHARD GARCIA |
| Plan Check Approved | 6/12/2023 | RICHARD GARCIA |
| Issued | 7/25/2023 | APPLICANT |
| Permit Finaled | 9/26/2024 | CLAUDIO MORENO |
| CofO Issued | 9/26/2024 | CLAUDIO MORENO |
| Permit Finaled | 9/26/2024 | CLAUDIO MORENO |
Permit Application Clearance Information
| Specific Plan | Cleared | 4/18/2023 | JIMMY VIVAR |
| Address approval | Cleared | 6/1/2023 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2023 | DINAH GARIN |
| Sewer availability | Cleared | 6/1/2023 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 11/2/2023 | Not Ready for Inspection | RYAN BARNES |
| Green Building Rough | 11/2/2023 | Not Ready for Inspection | RYAN BARNES |
| PLUMBING-Rough | 11/2/2023 | Not Ready for Inspection | RYAN BARNES |
| ELECTRICAL-Rough | 1/4/2024 | Corrections Issued | RYAN BARNES |
| PLUMBING-Final | 1/4/2024 | Partial Approval | RYAN BARNES |
| Drywall Nailing | 1/16/2024 | Approved | RYAN BARNES |
| ELECTRICAL-Final | 1/16/2024 | Not Ready for Inspection | RYAN BARNES |
| ELECTRICAL-Final | 2/20/2024 | Not Ready for Inspection | RYAN BARNES |
| Insulation | 2/21/2024 | Approved | RYAN BARNES |
| Interior/Exterior Lathing | 2/21/2024 | Approved | RYAN BARNES |
| Service/Power Release | 2/21/2024 | Approved | RYAN BARNES |
| BUILDING-Rough-Frame | 5/14/2024 | Approved | RYAN BARNES |
| Final | 5/14/2024 | Corrections Issued | RYAN BARNES |
| Green Building Final | 5/14/2024 | Approved | RYAN BARNES |
| Green Building Rough | 5/14/2024 | Approved | RYAN BARNES |
| SGSOV-Seismic Gas S/O Valve | 5/14/2024 | SGSOV Not Ready | RYAN BARNES |
| Smoke Detectors | 5/14/2024 | Approved | RYAN BARNES |
| Final | 7/24/2024 | Conditional Approval | RYAN BARNES |
| SGSOV-Seismic Gas S/O Valve | 7/24/2024 | SGSOV Approved | RYAN BARNES |