164 N BRISTOL AVE 90049
Certificate Information: 164 N BRISTOL AVE 90049
- Application / Permit
- 22016-30000-35167
- Plan Check / Job No.
- B22WL04303
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- replacing 2 exterior doors with 1 (n) bi-fold door per eng. calcs., remove steel SMF column in the middle & add new steel beam
- Permit Issued
- Issued on 1/23/2023
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 6/7/2024
Permit Application Status History
| Submitted | 11/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/23/2022 | HOOMAN HAJIZADEH |
| Corrections Issued | 12/2/2022 | HOOMAN HAJIZADEH |
| Quality Review Completed | 12/6/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 12/7/2022 | APPLICANT |
| Plan Check Approved | 1/23/2023 | HOOMAN HAJIZADEH |
| Issued | 1/23/2023 | APPLICANT |
| Permit Finaled | 6/7/2024 | ARAM AVEDISIAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Lannen Construction Inc; Lic. No.: 811038-B | 1545 SAWTELLE BLVD STE 22 LOS ANGELES, CA 90025 |
| Engineer | Naraghi-Arani,, Kamran; Lic. No.: C40985 | 30423 CANWOOD ST STE 223 AGOURA HILLS, CA 91301 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 4/10/2023 | Corrections Issued | KEVIN SARGSYAN |
| Deputy Wood Construction | 4/13/2023 | No Access for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2023 | Partial Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 4/25/2023 | Conditional Approval | MICHAEL PELHAM |
| ELECTRICAL-Rough | 4/26/2023 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 4/26/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2023 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 5/15/2023 | Partial Approval | KEVIN SARGSYAN |
| Deputy Steel/Welding | 5/26/2023 | Approved | KEVIN SARGSYAN |
| Structural Steel Frame | 5/26/2023 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 10/3/2023 | Conditional Approval | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 10/12/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 10/17/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 10/17/2023 | Approved | ARAM AVEDISIAN |
| Final | 6/7/2024 | Permit Finaled | ARAM AVEDISIAN |