946-948 N CROFT AVE 90069

Certificate Information: 946-948 N CROFT AVE 90069

Application / Permit
22016-30000-34091
Plan Check / Job No.
B22WL04147
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Interior / exterior alteration to (e) 2-story duplex
Permit Issued
Issued on 3/23/2023
Issuing Office
West Los Angeles
Current Status
Issued on 3/23/2023

Permit Application Status History

Submitted 11/9/2022 APPLICANT
Assigned to Plan Check Engineer 11/17/2022 REZA HAGHIGHAT
Corrections Issued 11/19/2022 REZA HAGHIGHAT
Quality Review Completed 11/27/2022 KAVIAN REFAHI
Building Plans Picked Up 11/28/2022 APPLICANT
Plan Check Approved 3/23/2023 REZA HAGHIGHAT
Issued 3/23/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/26/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 11/29/2022 STEVE MELGAR
Sewer availability Cleared 11/29/2022 STEVE MELGAR
"Q" conditions Cleared 12/1/2022 NATHAN ROMINE

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Owner-Builder       ,
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 10/5/2023 Corrections Issued LILIANA PORTILLO
HVAC-Rough 10/5/2023 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 10/5/2023 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 10/19/2023 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 10/19/2023 Partial Approval LILIANA PORTILLO
HVAC-Rough 10/19/2023 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 10/19/2023 Partial Approval LILIANA PORTILLO
BUILDING-Rough-Frame 10/31/2023 Partial Approval LILIANA PORTILLO
Green Building Rough 10/31/2023 Partial Approval LILIANA PORTILLO
Insulation 10/31/2023 Partial Approval LILIANA PORTILLO
Interior/Exterior Lathing 10/31/2023 Partial Approval LILIANA PORTILLO
Shower Pan 10/31/2023 Partial Approval LILIANA PORTILLO
Drywall Nailing 11/15/2023 Partial Approval LILIANA PORTILLO
PLUMBING-Final 3/8/2024 Not Ready for Inspection AMIR NAZARIAN
PLUMBING-Rough 3/8/2024 Not Ready for Inspection AMIR NAZARIAN
Deputy Drilled-In Anchors 4/25/2025 Conditional Approval JOSE MACIAS
Footing/Foundation/Slab 4/25/2025 Corrections Issued JOSE MACIAS
Footing/Foundation/Slab 5/1/2025 Approved WAYNE REGESTER
BUILDING-Rough-Frame 6/25/2025 No Access for Inspection JOSE MACIAS
Rough-Elec/Plmb/HVAC 6/25/2025 No Access for Inspection JOSE MACIAS
BUILDING-Rough-Frame 6/26/2025 Corrections Issued JOSE MACIAS
ELECTRICAL-Rough 6/26/2025 Approved JOSE MACIAS
BUILDING-Rough-Frame 7/22/2025 Approved JOSE MACIAS
ELECTRICAL-Rough 7/22/2025 Approved JOSE MACIAS
HVAC-Rough 7/22/2025 Approved JOSE MACIAS
PLUMBING-Rough 7/22/2025 Approved JOSE MACIAS
Insulation 7/31/2025 Corrections Issued JOSE MACIAS
Interior/Exterior Lathing 7/31/2025 Corrections Issued JOSE MACIAS
Shower Pan 7/31/2025 Approved JOSE MACIAS
Interior/Exterior Lathing 8/4/2025 Approved JOSE MACIAS
Drywall Nailing 8/7/2025 Corrections Issued WAYNE REGESTER
Drywall Nailing 8/11/2025 Approved JOSE MACIAS
Insulation 8/11/2025 Approved JOSE MACIAS