1530 S WALNUT AVE 90291

Certificate Information: 1530 S WALNUT AVE 90291

Application / Permit
22016-30000-27743
Plan Check / Job No.
B22WL03501
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL OF (E) 2 BEDROOM SFD
Permit Issued
Issued on 4/21/2023
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 6/18/2024

Permit Application Status History

Submitted 9/19/2022 APPLICANT
Assigned to Plan Check Engineer 9/22/2022 YASHAR EMAMI
Corrections Issued 10/5/2022 YASHAR EMAMI
Quality Review Completed 10/16/2022 KAVIAN REFAHI
Building Plans Picked Up 10/19/2022 APPLICANT
Applicant returned to address corrections 1/4/2023 CHIHARU SUZUKI
Applicant returned to address corrections 1/18/2023 YASHAR EMAMI
Applicant returned to address corrections 3/30/2023 YASHAR EMAMI
Plan Check Approved 4/19/2023 YASHAR EMAMI
Issued 4/21/2023 APPLICANT
Permit Finaled 6/18/2024 HERBERT GIRON

Permit Application Clearance Information

Specific Plan Cleared 12/5/2022 JAZMIN ROQUE
Permit Cleared 12/6/2022 AHMED AMARRAGY
Roof/Waste drainage to street Cleared 12/6/2022 AHMED AMARRAGY
Eng Process Fee Ord 176,300 Cleared 12/12/2022 AHMED AMARRAGY
Sewer availability Cleared 12/12/2022 AHMED AMARRAGY
Hydrant and Access approval Cleared 12/17/2022 KURT CORRAL
Trees in Parkway Cleared 12/22/2022 ADALBERTO VERA
Low Impact Development Cleared 3/9/2023 MARCO SANCHEZ

Contact Information

Architect Stage,, Christopher Barrett; Lic. No.: C32866 10815 OREGON AVENUE      CULVER CITY, CA 90232
Contractor K N Construction; Lic. No.: 1001762-B 20233 OBSERVATION DR      TOPANGA, CA 90290
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/26/2023 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 5/30/2023 Conditional Approval EVAN COOPER
Deputy Drilled-In Anchors 7/11/2023 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 8/15/2023 Approved HERBERT GIRON
Insulation 8/24/2023 Not Ready for Inspection TEMISTOCLES CAAL
PLUMBING-Rough 8/24/2023 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 9/11/2023 Corrections Issued HERBERT GIRON
PLUMBING-Rough 10/12/2023 Approved TEMISTOCLES CAAL
Gas Test 11/7/2023 Corrections Issued HERBERT GIRON
HVAC-Rough 11/7/2023 Partial Approval HERBERT GIRON
Underground Mechanical 11/7/2023 Partial Approval HERBERT GIRON
ELECTRICAL-Rough 11/13/2023 Partial Approval HERBERT GIRON
Gas Test 12/4/2023 Corrections Issued HERBERT GIRON
HVAC-Rough 12/4/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 12/6/2023 Partial Approval HERBERT GIRON
Gas Test 12/6/2023 Partial Approval HERBERT GIRON
HVAC-Rough 12/6/2023 Conditional Approval HERBERT GIRON
ELECTRICAL-Rough 12/7/2023 Approved HERBERT GIRON
Insulation 12/7/2023 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 12/11/2023 Approved HERBERT GIRON
Footing/Foundation/Slab 12/11/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 1/16/2024 Approved HERBERT GIRON
Green Building Rough 1/16/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 1/16/2024 Partial Approval HERBERT GIRON
Insulation 1/22/2024 Approved TEMISTOCLES CAAL
Drywall Nailing 1/31/2024 Approved HERBERT GIRON
Shower Pan 2/23/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 3/7/2024 Approved HERBERT GIRON
Gas Test 5/15/2024 Approved HERBERT GIRON
PLUMBING-Final 5/30/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 6/11/2024 Approved HERBERT GIRON
HVAC-Final 6/11/2024 Corrections Issued HERBERT GIRON
PLUMBING-Final 6/11/2024 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 6/11/2024 SGSOV Approved HERBERT GIRON
Smoke Detectors 6/11/2024 Approved HERBERT GIRON
Final 6/18/2024 Permit Finaled HERBERT GIRON
HVAC-Final 6/18/2024 Approved HERBERT GIRON
Service/Power Release 6/18/2024 Approved HERBERT GIRON