12327 W STANWOOD DR 90066
Certificate Information: 12327 W STANWOOD DR 90066
- Application / Permit
- 22016-30000-26939
- Plan Check / Job No.
- B22WL03418
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior structural remodel of an (e) S.F.D. The work to include remodel of kitchen/dinning/ living room, remodel of bathrooms and new bedroom to replace existing den.
- Permit Issued
- Issued on 11/21/2022
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 5/3/2023
Permit Application Status History
| Submitted | 9/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2022 | RICHARD GARCIA |
| Corrections Issued | 9/14/2022 | RICHARD GARCIA |
| Building Plans Picked Up | 9/16/2022 | APPLICANT |
| Plan Check Approved | 10/12/2022 | EDWIN ESPIN |
| Issued | 11/21/2022 | APPLICANT |
| Permit Finaled | 5/2/2023 | JOHNNY MIRANDA |
Permit Application Clearance Information
| Sewer availability | Cleared | 9/20/2022 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2022 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 9/29/2022 | KIRK LINKLATER |
Contact Information
| Architect | Asamoah,, B Kwesi; Lic. No.: C36558 | 850 ROSE AVENUE VENICE, CA 90291 |
| Contractor | Golden Lion; Lic. No.: 687458-B | 8005 MC GROARTY SUNLAND, CA 91040 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/14/2022 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 12/16/2022 | Approved | JOHNNY MIRANDA |
| Piling/Pier/Caisson | 12/16/2022 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 2/21/2023 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 2/21/2023 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 2/21/2023 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 2/21/2023 | Corrections Issued | JOHNNY MIRANDA |
| Insulation | 2/28/2023 | Approved | CLAYTON GRAHAM |
| PLUMBING-Rough | 2/28/2023 | Approved | CLAYTON GRAHAM |
| Drywall Nailing | 3/6/2023 | Approved | JOHNNY MIRANDA |
| Shower Pan | 3/6/2023 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 4/24/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 4/24/2023 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 4/24/2023 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 4/24/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 4/27/2023 | Approved | EVAN COOPER |
| PLUMBING-Final | 4/27/2023 | Corrections Issued | EVAN COOPER |
| Final | 5/2/2023 | Permit Finaled | JOHNNY MIRANDA |