2673 N ZORADA DR 90046

Certificate Information: 2673 N ZORADA DR 90046

Application / Permit
22016-30000-26916
Plan Check / Job No.
B22WL03404
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior and exterior remodel at 1st and 2nd Floor of an (E) 2-Story S.F.D w/an attached garage.
Permit Issued
Issued on 7/19/2023
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 3/29/2024

Permit Application Status History

Submitted 9/6/2022 APPLICANT
Assigned to Plan Check Engineer 9/12/2022 DAVID CASTILLO
Corrections Issued 9/13/2022 DAVID CASTILLO
Building Plans Picked Up 9/19/2022 APPLICANT
Applicant returned to address corrections 3/23/2023 JOHNPAUL ISIP
Plan Check Approved 3/28/2023 RICHARD GARCIA
Issued 7/19/2023 APPLICANT
Permit Finaled 3/28/2024 BRIAN SULLIVAN

Permit Application Clearance Information

Specific Plan Cleared 3/2/2023 OLGA AYALA
Grading Pre-Inspection Cleared 3/28/2023 DAVID CASTILLO

Contact Information

Contractor Racing Green Group Deep Grey Foundations; Lic. No.: 992206-C10 13123 W WASHINGTON BLVD      LOS ANGELES, CA 90066
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 2999 OVERLAND AVE STE 103      LOS ANGELES, CA 90064

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/25/2023 Conditional Approval STUART CHAPMAN
ELECTRICAL-Rough 7/26/2023 Not Ready for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 7/26/2023 Approved RAUL BARAJAS
Footing/Foundation/Slab 7/26/2023 Approved RAUL BARAJAS
HVAC-Rough 7/26/2023 Partial Inspection RAUL BARAJAS
PLUMBING-Rough 7/26/2023 Partial Approval RAUL BARAJAS
BUILDING-Rough-Frame 10/10/2023 Corrections Issued RAUL BARAJAS
ELECTRICAL-Rough 10/10/2023 Approved RAUL BARAJAS
HVAC-Rough 10/10/2023 Partial Approval RAUL BARAJAS
Interior/Exterior Lathing 10/10/2023 Approved RAUL BARAJAS
PLUMBING-Rough 10/10/2023 Partial Inspection RAUL BARAJAS
Shower Pan 10/10/2023 Approved RAUL BARAJAS
Structural Steel Frame 10/10/2023 Partial Approval RAUL BARAJAS
Wood Frame 10/10/2023 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 10/13/2023 Approved STUART CHAPMAN
Insulation 10/19/2023 Approved STUART CHAPMAN
BUILDING-Rough-Frame 10/26/2023 Corrections Issued STUART CHAPMAN
Interior/Exterior Lathing 10/26/2023 Partial Approval STUART CHAPMAN
Structural Steel Frame 10/26/2023 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 10/27/2023 Approved STUART CHAPMAN
PLUMBING-Rough 10/27/2023 Approved STUART CHAPMAN
Drywall Nailing 11/27/2023 Approved BRIAN SULLIVAN
Drywall Nailing 12/19/2023 Approved STUART CHAPMAN
Final 3/18/2024 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 3/18/2024 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 3/18/2024 Approved CRAIG VAUGHAN
ELECTRICAL-Final 3/28/2024 Approved BRIAN SULLIVAN
Final 3/28/2024 Permit Finaled BRIAN SULLIVAN
HVAC-Final 3/28/2024 Approved BRIAN SULLIVAN
PLUMBING-Final 3/28/2024 Approved BRIAN SULLIVAN