3343 S CARDIFF AVE 90034

Certificate Information: 3343 S CARDIFF AVE 90034

Application / Permit
22016-30000-26682
Plan Check / Job No.
B22WL03371
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Detached garage conversion into an ADU.
Permit Issued
Issued on 1/25/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/2/2022 APPLICANT
Assigned to Plan Check Engineer 9/12/2022 RICHARD GARCIA
Corrections Issued 9/12/2022 RICHARD GARCIA
Building Plans Picked Up 9/13/2022 APPLICANT
Plan Check Approved 11/30/2022 RICHARD GARCIA
Issued 1/25/2023 APPLICANT
CofO in Progress 12/6/2023 MICHAEL PELHAM
Permit Finaled 12/6/2023 DANIEL ORRANTE
CofO Issued 12/6/2023 DANIEL ORRANTE
Permit Finaled 12/6/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 11/10/2022 NIKTA MOUSAVI
Sewer availability Cleared 11/10/2022 NIKTA MOUSAVI
Eng Process Fee Ord 176,300 Cleared 11/18/2022 NIKTA MOUSAVI
Grading Pre-Inspection Cleared 11/30/2022 RICHARD GARCIA

Contact Information

Contractor Eberia Construction Inc; Lic. No.: 701330-B 8924 OLIN STREET      LOS ANGELES, CA 90034
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 2999 OVERLAND AVE STE 103      LOS ANGELES, CA 90064

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/31/2023 Not Ready for Inspection JESUS RODRIGUEZ
Footing/Foundation/Slab 2/16/2023 Corrections Issued ASHLEY THOMPSON
Deputy Drilled-In Anchors 2/21/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 2/23/2023 Partial Approval JOHNNY MIRANDA
Footing/Foundation/Slab 2/28/2023 Not Ready for Inspection MICHAEL PELHAM
PLUMBING-Rough 2/28/2023 Partial Approval MICHAEL PELHAM
BUILDING-Rough-Frame 3/3/2023 Corrections Issued ASHLEY THOMPSON
Footing/Foundation/Slab 3/3/2023 Approved ASHLEY THOMPSON
ELECTRICAL-Rough 3/28/2023 Corrections Issued JEREMY TODD
HVAC-Rough 3/28/2023 Not Ready for Inspection JEREMY TODD
PLUMBING-Rough 3/28/2023 Not Ready for Inspection JEREMY TODD
ELECTRICAL-Rough 3/30/2023 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 3/30/2023 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 3/30/2023 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 4/12/2023 Approved JEREMY TODD
Underground Mechanical 4/12/2023 Approved JEREMY TODD
Wood Frame 4/12/2023 Approved JEREMY TODD
Interior/Exterior Lathing 5/9/2023 Approved CLAYTON GRAHAM
ELECTRICAL-Rough 5/19/2023 Approved CLAYTON GRAHAM
Insulation 5/19/2023 Corrections Issued CLAYTON GRAHAM
Insulation 6/22/2023 Corrections Issued DAVID FEILER
Insulation 7/18/2023 Corrections Issued CLAYTON GRAHAM
Shower Pan 7/18/2023 Approved CLAYTON GRAHAM
BUILDING-Rough-Frame 7/21/2023 Approved DAVID FEILER
Green Building Rough 7/21/2023 Approved DAVID FEILER
Insulation 7/21/2023 Approved DAVID FEILER
MERV13>=Rough 7/21/2023 Approved DAVID FEILER
Rough-Elec/Plmb/HVAC 7/21/2023 Approved DAVID FEILER
Green Building Rough 7/31/2023 Approved CLAYTON GRAHAM
PLUMBING-Rough 7/31/2023 Corrections Issued CLAYTON GRAHAM
Drywall Nailing 8/9/2023 Partial Approval CLAYTON GRAHAM
HVAC-Final 8/9/2023 Corrections Issued CLAYTON GRAHAM
HVAC-Rough 8/9/2023 Approved CLAYTON GRAHAM
PLUMBING-Rough 8/9/2023 Approved CLAYTON GRAHAM
Drywall Nailing 8/17/2023 Approved CLAYTON GRAHAM
Interior/Exterior Lathing 8/17/2023 Approved CLAYTON GRAHAM
HVAC-Final 9/11/2023 Corrections Issued CLAYTON GRAHAM
ELECTRICAL-Final 10/12/2023 Corrections Issued CLAYTON GRAHAM
PLUMBING-Final 10/12/2023 Corrections Issued CLAYTON GRAHAM
ELECTRICAL-Final 10/23/2023 Corrections Issued CLAYTON GRAHAM
Final 10/23/2023 Corrections Issued CLAYTON GRAHAM
Green Building Final 10/23/2023 Approved CLAYTON GRAHAM
MERV13>=Final 10/23/2023 Approved CLAYTON GRAHAM
PLUMBING-Final 10/23/2023 Corrections Issued CLAYTON GRAHAM
SGSOV-Seismic Gas S/O Valve 10/23/2023 SGSOV Approved CLAYTON GRAHAM
Smoke Detectors 10/23/2023 Approved CLAYTON GRAHAM
ELECTRICAL-Final 10/25/2023 Approved CLAYTON GRAHAM
Final 12/4/2023 Conditional Approval MICHAEL PELHAM