527 S BARRINGTON AVE 90049

Certificate Information: 527 S BARRINGTON AVE 90049

Application / Permit
22016-30000-25381
Plan Check / Job No.
B22WL03207
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
2nd floor balcony water damage repair. Providing (n) floor joists, steel columns & beams w/ new foundation per engineer's calcs.
Permit Issued
Issued on 6/5/2023
Issuing Office
Valley
Current Status
Permit Finaled on 9/11/2023

Permit Application Status History

Submitted 8/22/2022 APPLICANT
Assigned to Plan Check Engineer 8/31/2022 EDWIN ESPIN
Corrections Issued 9/1/2022 EDWIN ESPIN
Building Plans Picked Up 9/12/2022 APPLICANT
Applicant returned to address corrections 3/7/2023 AMY GUEVARRA
Plan Check Approved 3/14/2023 ALFREDO JARA
Issued 6/5/2023 APPLICANT
Permit Finaled 9/7/2023 FARHAD DADBIN

Permit Application Clearance Information

Tenant Habitability Plan Cleared 2/9/2023 ISMAEL HERNANDEZ
Grading Pre-Inspection Cleared 3/7/2023 EDWIN ESPIN
Miscellaneous Cleared 3/7/2023 EDWIN ESPIN

Contact Information

Contractor Sater Development Strategies Inc; Lic. No.: 1074535-B 9854 NATIONAL BLVD 235      LOS ANGELES, CA 90034
Engineer Alexander,, Andy; Lic. No.: C84086 1615 GRAMERCY AVE      TORRANCE, CA 90501

Inspector Information

CASIMIR BRITTON, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI
SHAVONNE ESPINOZA, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/22/2023 Partial Approval ALAN NOVAK
Deputy Steel/Welding 6/23/2023 Conditional Approval GRANT WOODS
Deputy Reinf. Concrete 6/26/2023 Conditional Approval ALAN NOVAK
Structural Steel Frame 7/17/2023 Approved ALAN NOVAK
Wood Frame 7/17/2023 Approved ALAN NOVAK
Drywall Nailing 7/20/2023 Approved ALAN NOVAK
Interior/Exterior Lathing 7/20/2023 Approved ALAN NOVAK
Interior/Exterior Lathing 7/25/2023 Partial Inspection SORIN CIRSTOIU
Interior/Exterior Lathing 8/8/2023 Partial Inspection SORIN CIRSTOIU
Final 8/30/2023 Not Ready for Inspection MICHAEL PETRUSKO
SGSOV-Seismic Gas S/O Valve 8/30/2023 SGSOV Not Ready MICHAEL PETRUSKO
Smoke Detectors 8/30/2023 Not Ready for Inspection MICHAEL PETRUSKO
Final 9/7/2023 Permit Finaled FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 9/7/2023 SGSOV Approved FARHAD DADBIN
Smoke Detectors 9/7/2023 Approved FARHAD DADBIN