655 W ANGELUS PL 90291
Certificate Information: 655 W ANGELUS PL 90291
- Application / Permit
- 22016-30000-24754
- Plan Check / Job No.
- B22WL03143
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-story addition (303 sf) to rear side of (e) single story SFD (947 sf)
- Permit Issued
- Issued on 12/28/2022
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 8/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | REZA HAGHIGHAT |
| Corrections Issued | 8/30/2022 | REZA HAGHIGHAT |
| Quality Review Completed | 9/12/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 9/19/2022 | APPLICANT |
| Plan Check Approved | 12/13/2022 | REZA HAGHIGHAT |
| Issued | 12/28/2022 | APPLICANT |
| CofO in Progress | 8/4/2023 | JESUS RODRIGUEZ |
| Permit Finaled | 8/15/2023 | DANIEL ORRANTE |
| CofO Issued | 8/15/2023 | DANIEL ORRANTE |
| Permit Finaled | 8/15/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/21/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 9/21/2022 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2022 | CATHERINE ADROVER |
| Coastal Zone | Cleared | 11/4/2022 | SPENCER WEJROWSKI |
| ZA Case | Cleared | 11/4/2022 | SPENCER WEJROWSKI |
| ZA Case | Cleared | 11/4/2022 | SPENCER WEJROWSKI |
| Specific Plan | Cleared | 12/12/2022 | JULIET OH |
Contact Information
| Architect | Le, Clerc, Sarah Jane; Lic. No.: C39716 | 1134 CHELSEA AVE #B SANTA MONICA, CA 90403 |
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/1/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 2/6/2023 | Corrections Issued | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 2/16/2023 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 2/16/2023 | Partial Approval | EVAN COOPER |
| Deputy Wood Construction | 3/17/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2023 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 3/31/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 4/6/2023 | No Access for Inspection | KENNETH NAGLE |
| PLUMBING-Rough | 4/6/2023 | No Access for Inspection | KENNETH NAGLE |
| HVAC-Rough | 4/7/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 4/7/2023 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 4/7/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 4/11/2023 | Approved | KENNETH NAGLE |
| ELECTRICAL-Rough | 4/11/2023 | Approved | KENNETH NAGLE |
| Green Building Rough | 4/11/2023 | Approved | KENNETH NAGLE |
| Drywall Nailing | 4/17/2023 | Approved | EVAN COOPER |
| Insulation | 4/17/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 4/17/2023 | Approved | EVAN COOPER |
| Service/Power Release | 6/5/2023 | Approved | EVAN COOPER |
| Final | 6/26/2023 | Corrections Issued | EVAN COOPER |
| Green Building Final | 6/26/2023 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 6/26/2023 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 6/26/2023 | Approved | EVAN COOPER |
| Final | 8/1/2023 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Final | 8/4/2023 | Approved | JESUS RODRIGUEZ |
| Final | 8/4/2023 | OK to Issue CofO | JESUS RODRIGUEZ |
| HVAC-Final | 8/4/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 8/4/2023 | Approved | JESUS RODRIGUEZ |