852-852 1/2 N ROME DR 90065

Certificate Information: 852-852 1/2 N ROME DR 90065

Application / Permit
22016-30000-23369
Plan Check / Job No.
B22WL03003
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel of (E) 2-Story S.F.D w/Attached Carport Conversion to JADU per GCS 65852.2(e)(1)(A) and 65852.22
Permit Issued
Issued on 10/13/2022
Issuing Office
Metro
Current Status
CofO Issued on 12/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2022 APPLICANT
Assigned to Plan Check Engineer 8/17/2022 DAVID CASTILLO
Corrections Issued 8/18/2022 DAVID CASTILLO
Applicant returned to address corrections 10/5/2022 EDWIN ESPIN
Building Plans Picked Up 10/6/2022 APPLICANT
Applicant returned to address corrections 10/7/2022 LAWRENCE QUIRANTE
Issued 10/13/2022 APPLICANT
CofO in Progress 12/7/2024 ALIZAH MAYAGOITIA
Permit Finaled 12/12/2024 DEROLD HAUFF
CofO Issued 12/12/2024 DEROLD HAUFF
Permit Finaled 12/12/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/25/2022 TREVOR QUAN
Roof/Waste drainage to street Cleared 8/25/2022 TREVOR QUAN
Sewer availability Cleared 8/25/2022 TREVOR QUAN
Tenant Habitability Plan Cleared 8/25/2022 MICHAEL SOTO
Eng Process Fee Ord 176,300 Cleared 8/26/2022 TREVOR QUAN
Specific Plan Cleared 9/6/2022 NASHYA JENSEN
Grading Pre-Inspection Cleared 9/9/2022 KIRK LINKLATER

Contact Information

Architect Taalman,, Linda Evelyn; Lic. No.: C30187 2902 ROWENA AVENUE      LOS ANGELES, CA 90039
Contractor Owner-Builder       ,
Engineer Phillips,, Craig; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/8/2023 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 2/27/2023 Partial Approval JOSEPH MCGARRY
Sewer 2/27/2023 Approved JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 3/28/2023 Approved OSVALDO PARAMO
Footing/Foundation/Slab 3/28/2023 Approved OSVALDO PARAMO
Deputy Steel/Welding 4/14/2023 Conditional Approval OSVALDO PARAMO
Deputy Drilled-In Anchors 4/19/2023 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 4/24/2023 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 4/27/2023 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 7/13/2023 Corrections Issued SCOTT FINNILA
Underground Mechanical 7/13/2023 Partial Approval SCOTT FINNILA
HVAC-Rough 7/14/2023 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 7/14/2023 Corrections Issued OSVALDO PARAMO
BUILDING-Rough-Frame 7/25/2023 Corrections Issued AMY COLIN
ELECTRICAL-Rough 7/25/2023 Approved AMY COLIN
HVAC-Rough 7/25/2023 Approved AMY COLIN
PLUMBING-Rough 7/25/2023 Partial Approval AMY COLIN
Insulation 7/28/2023 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 7/31/2023 Partial Approval BRENDAN MORELLI
Insulation 7/31/2023 Not Ready for Inspection BRENDAN MORELLI
BUILDING-Rough-Frame 8/21/2023 Approved OSVALDO PARAMO
Interior/Exterior Lathing 8/21/2023 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 8/21/2023 Approved OSVALDO PARAMO
Insulation 8/31/2023 Approved OSVALDO PARAMO
Shower Pan 8/31/2023 Approved OSVALDO PARAMO
Drywall Nailing 9/26/2023 Approved OSVALDO PARAMO
Interior/Exterior Lathing 9/26/2023 Approved OSVALDO PARAMO
Final 8/28/2024 Corrections Issued ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 8/28/2024 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 8/28/2024 Corrections Issued LUIS CASTRO
ELECTRICAL-Final 9/5/2024 Corrections Issued OSVALDO PARAMO
HVAC-Final 9/5/2024 Corrections Issued OSVALDO PARAMO
PLUMBING-Final 9/5/2024 Approved OSVALDO PARAMO
Smoke Detectors 9/5/2024 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Final 9/13/2024 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Final 9/16/2024 Approved OSVALDO PARAMO
Final 11/15/2024 Corrections Issued ALIZAH MAYAGOITIA
HVAC-Final 11/15/2024 Approved ALIZAH MAYAGOITIA
Smoke Detectors 11/15/2024 Approved ALIZAH MAYAGOITIA
Final 11/21/2024 Partial Approval ALIZAH MAYAGOITIA
Final 12/7/2024 OK to Issue CofO ALIZAH MAYAGOITIA