1824 S FAIRBURN AVE 101 90025

Certificate Information: 1824 S FAIRBURN AVE 101 90025

Application / Permit
22016-30000-22741
Plan Check / Job No.
B22WL02940
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Rec room conversion to ADU per GCS 65852.2(e)(1)(C)
Permit Issued
Issued on 9/17/2024
Issuing Office
Current Status
Issued on 9/17/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/29/2022 APPLICANT
Assigned to Plan Check Engineer 8/5/2022 EDWIN ESPIN
Corrections Issued 8/6/2022 EDWIN ESPIN
Applicant returned to address corrections 10/5/2022 RICHARD GARCIA
Applicant returned to address corrections 3/1/2023 AMY GUEVARRA
Plan Check Approved 3/17/2023 DAVID CASTILLO
Issued 9/17/2024 APPLICANT

Permit Application Clearance Information

Specific Plan Cleared 9/14/2022 KENTON TRINH
ZI Cleared 9/14/2022 KENTON TRINH
Sewer availability Cleared 9/15/2022 JENSON LEE
Public Works-Highway Ded. Cleared 9/15/2022 JENSON LEE
Public Works-Open Permits Cleared 9/15/2022 JENSON LEE
Public Works-Sewers Cleared 9/15/2022 JENSON LEE
Address approval Cleared 9/21/2022 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 9/21/2022 JENSON LEE
Specific Plan Cleared 9/27/2022 PEDRO AYALA
Tenant Habitability Plan Cleared 3/13/2023 ISMAEL HERNANDEZ

Contact Information

Architect Diaz,, Richard E; Lic. No.: C34030 2219 MAIN ST #206      SANTA MONICA, CA 90405
Contractor Trochez Construction Inc; Lic. No.: 1097458-B 227 E 43RD STREET      LOS ANGELES, CA 90011

Inspector Information

ROGELIO REYNA, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 2/6/2025 Not Ready for Inspection RICARDO ROBLES
Final 2/6/2025 Not Ready for Inspection RICARDO ROBLES
METHANE-Final 2/6/2025 Not Ready for Inspection RICARDO ROBLES
METHANE-Rough 2/6/2025 Not Ready for Inspection RICARDO ROBLES
SGSOV-Seismic Gas S/O Valve 2/6/2025 SGSOV Not Ready RICARDO ROBLES
Smoke Detectors 2/6/2025 Not Ready for Inspection RICARDO ROBLES
Wood Frame 2/6/2025 Partial Approval RICARDO ROBLES
METHANE-Rough 3/14/2025 Approved RICARDO ROBLES
Pre-Inspection 3/14/2025 Not Ready for Inspection RICARDO ROBLES
Interior/Exterior Lathing 3/25/2025 Approved VASIL MIHALEV
Drywall Nailing 4/21/2025 Not Ready for Inspection VASIL MIHALEV
Wood Frame 4/21/2025 Partial Approval VASIL MIHALEV
Excavation/Setback/Form/Re-Bar 5/6/2025 Not Ready for Inspection RICARDO ROBLES
Drywall Nailing 5/7/2025 Approved RICARDO ROBLES
Wood Frame 5/7/2025 Approved RICARDO ROBLES
Final 1/8/2026 Not Ready for Inspection RICARDO ROBLES
SGSOV-Seismic Gas S/O Valve 1/8/2026 SGSOV Approved RICARDO ROBLES
Smoke Detectors 1/8/2026 Approved RICARDO ROBLES