6409 W 80TH PL 90045
Certificate Information: 6409 W 80TH PL 90045
- Application / Permit
- 22016-30000-22113
- Plan Check / Job No.
- B22WL02852
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior and exterior remodel of (E) 1-Story S.F.D. Remodel bedrooms, kitchen and bathrooms.
- Permit Issued
- Issued on 8/17/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 2/16/2023
Permit Application Status History
| Submitted | 7/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/26/2022 | DAVID CASTILLO |
| Corrections Issued | 7/26/2022 | DAVID CASTILLO |
| Building Plans Picked Up | 7/28/2022 | APPLICANT |
| Plan Check Approved | 8/16/2022 | RICARDO RAMIREZ |
| Issued | 8/17/2022 | APPLICANT |
| Permit Finaled | 2/16/2023 | JESUS RODRIGUEZ |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wong,, Jim Chu Man; Lic. No.: C69393 | PO BOX 373 GLENDORA, CA 91740 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/18/2022 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 10/24/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 11/18/2022 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 11/18/2022 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 11/18/2022 | Corrections Issued | HERBERT GIRON |
| Wood Frame | 11/18/2022 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 11/22/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 11/22/2022 | Approved | HERBERT GIRON |
| HVAC-Rough | 11/22/2022 | Conditional Approval | HERBERT GIRON |
| PLUMBING-Rough | 11/22/2022 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 12/5/2022 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2022 | Approved | HERBERT GIRON |
| Green Building Rough | 12/5/2022 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 12/7/2022 | Approved | HERBERT GIRON |
| Green Building Rough | 12/7/2022 | Approved | HERBERT GIRON |
| Insulation | 12/7/2022 | Approved | HERBERT GIRON |
| Drywall Nailing | 12/13/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 12/13/2022 | Partial Approval | HERBERT GIRON |
| Shower Pan | 12/13/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 12/19/2022 | Approved | CLAYTON GRAHAM |
| Gas Test | 1/27/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 2/6/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 2/7/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 2/7/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 2/8/2023 | Approved | RICHARD STEINBACH |
| ELECTRICAL-Final | 2/9/2023 | Approved | HERBERT GIRON |
| Final | 2/9/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 2/9/2023 | SGSOV Not Ready | HERBERT GIRON |
| Smoke Detectors | 2/9/2023 | Approved | HERBERT GIRON |
| Final | 2/16/2023 | Permit Finaled | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 2/16/2023 | SGSOV Approved | JESUS RODRIGUEZ |