2256 N DORRIS PL 90031

Certificate Information: 2256 N DORRIS PL 90031

Application / Permit
22016-30000-20108
Plan Check / Job No.
B22WL02640
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (e) det. garage to an ADU (552 sf) per LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 9/30/2022
Issuing Office
Current Status
CofO Issued on 6/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2022 APPLICANT
Assigned to Plan Check Engineer 7/14/2022 REZA HAGHIGHAT
Corrections Issued 7/17/2022 REZA HAGHIGHAT
Quality Review Completed 8/1/2022 CHIHARU SUZUKI
Plan Check Approved 9/22/2022 REZA HAGHIGHAT
Issued 9/30/2022 APPLICANT
Building Plans Picked Up 10/5/2022 APPLICANT
CofO in Progress 6/21/2024 HAMIK HARTOUNIAN
CofO Issued 6/25/2024 DEROLD HAUFF
Permit Finaled 6/25/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/17/2022 STEVE MELGAR
Permit Cleared 8/17/2022 STEVE MELGAR
Sewer availability Cleared 8/17/2022 STEVE MELGAR
ZI Cleared 8/17/2022 YINGSHI HUANG
Eng Process Fee Ord 176,300 Cleared 8/18/2022 STEVE MELGAR
Construction near power lines Cleared 9/14/2022 RIDWAN HARDY

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Level + Square Construction Fabrication; Lic. No.: 1046873-B 1714 N ORANGE GROVE AVE      LOS ANGELES, CA 90046

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/27/2023 Partial Approval JOSEPH MCGARRY
Underground Mechanical 4/27/2023 Partial Approval JOSEPH MCGARRY
Deputy Drilled-In Anchors 5/8/2023 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 5/8/2023 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 6/7/2023 Not Ready for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 6/7/2023 Approved THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 6/7/2023 Corrections Issued THOMAS LOGRASSO
Insulation 6/13/2023 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 6/15/2023 Partial Approval THOMAS LOGRASSO
Insulation 6/15/2023 Approved THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 6/15/2023 Partial Approval THOMAS LOGRASSO
Drywall Nailing 6/20/2023 Corrections Issued KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 6/20/2023 Corrections Issued KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 6/29/2023 Approved THOMAS LOGRASSO
Green Building Rough 6/29/2023 Not Ready for Inspection THOMAS LOGRASSO
Drywall Nailing 6/30/2023 Not Ready for Inspection THOMAS LOGRASSO
Drywall Nailing 7/7/2023 Approved THOMAS LOGRASSO
Green Building Rough 7/7/2023 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 7/13/2023 Partial Approval THOMAS LOGRASSO
Interior/Exterior Lathing 11/21/2023 Approved THOMAS LOGRASSO
Footing/Foundation/Slab 11/22/2023 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Final 1/5/2024 Not Ready for Inspection THOMAS LOGRASSO
Final 3/27/2024 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Final 4/11/2024 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 6/7/2024 Approved HAMIK HARTOUNIAN
Final 6/7/2024 Partial Inspection HAMIK HARTOUNIAN
Green Building Final 6/7/2024 Approved HAMIK HARTOUNIAN
MERV13>=Final 6/7/2024 Approved HAMIK HARTOUNIAN
MERV13>=Rough 6/7/2024 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 6/7/2024 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 6/7/2024 Approved HAMIK HARTOUNIAN
Final 6/21/2024 OK to Issue CofO HAMIK HARTOUNIAN
Service/Power Release 6/21/2024 Approved HAMIK HARTOUNIAN