15019-15021 W LEMAY ST 91405

Certificate Information: 15019-15021 W LEMAY ST 91405

Application / Permit
22016-30000-17210
Plan Check / Job No.
B22WL02293
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Garage Conversion to JADU per GCS 65852.2(e)(1)(A) and 65852.22 "COMPLY WITH DEPARTMENT ORDER effective date 04/14/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 9/1/2022
Issuing Office
Current Status
Issued on 9/1/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/8/2022 APPLICANT
Assigned to Plan Check Engineer 6/16/2022 DAVID CASTILLO
Corrections Issued 6/21/2022 DAVID CASTILLO
Plan Check Approved 7/12/2022 ALFREDO JARA
Issued 9/1/2022 APPLICANT
Building Plans Picked Up 9/8/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/28/2022 MEGAN GODINEZ
Sewer availability Cleared 6/28/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 7/13/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 7/13/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 7/13/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 7/13/2022 MEGAN GODINEZ

Contact Information

Architect Cuningham, Group Architecture Inc; Lic. No.: BUS13183 1030 G STREET      SAN DIEGO, CA 92101
Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 8/14/2023 Corrections Issued MICKEY YAMASHITA
ELECTRICAL-Rough 8/14/2023 Corrections Issued MICKEY YAMASHITA
Footing/Foundation/Slab 8/14/2023 Corrections Issued MICKEY YAMASHITA
ELECTRICAL-Rough 9/9/2025 Corrections Issued MICKEY YAMASHITA
PLUMBING-Rough 9/9/2025 Corrections Issued MICKEY YAMASHITA
Pre-Inspection 9/9/2025 Corrections Issued MICKEY YAMASHITA
Footing/Foundation/Slab 5/19/2026 Conditional Approval JOEL GUARDADO
BUILDING-Rough-Frame 5/29/2026 Conditional Approval JOEL GUARDADO
Rough-Elec/Plmb/HVAC 5/29/2026 Approved JOEL GUARDADO
BUILDING-Rough-Frame 6/23/2026 Conditional Approval MICKEY YAMASHITA
Floor/Roof Diaphrgm/Shear Wall 6/23/2026 Corrections Issued MICKEY YAMASHITA
Insulation 6/23/2026 Conditional Approval MICKEY YAMASHITA
Shower Pan 6/23/2026 Not Ready for Inspection MICKEY YAMASHITA
BUILDING-Rough-Frame 6/24/2026 Partial Approval MICKEY YAMASHITA
ELECTRICAL-Rough 6/24/2026 Approved MICKEY YAMASHITA
Floor/Roof Diaphrgm/Shear Wall 6/24/2026 Approved MICKEY YAMASHITA
Green Building Rough 6/24/2026 Approved MICKEY YAMASHITA
Insulation 6/24/2026 Approved MICKEY YAMASHITA
BUILDING-Rough-Frame 7/2/2026 Approved MICKEY YAMASHITA
Drywall Nailing 7/2/2026 Corrections Issued MICKEY YAMASHITA
Interior/Exterior Lathing 7/2/2026 Not Ready for Inspection MICKEY YAMASHITA
Shower Pan 7/2/2026 Conditional Approval MICKEY YAMASHITA
Drywall Nailing 7/15/2026 Approved MICKEY YAMASHITA
HVAC-Rough 7/15/2026 Corrections Issued MICKEY YAMASHITA
Shower Pan 7/15/2026 Approved MICKEY YAMASHITA