1663 SAWTELLE BLVD 90025
Certificate Information: 1663 SAWTELLE BLVD 90025
- Application / Permit
- 22016-30000-16727
- Plan Check / Job No.
- B22WL02239
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- Interior TI and add a new elevator to existing 3-story office building with retail and parking at 1st floor and 1 level basement parking. Relocate parking stalls with no change in number or type.
- Permit Issued
- Issued on 6/7/2023
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 3/13/2026
Permit Application Status History
| Submitted | 6/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2022 | REZA HAGHIGHAT |
| Corrections Issued | 6/19/2022 | REZA HAGHIGHAT |
| Quality Review Completed | 7/1/2022 | TARIK SAOUD |
| Building Plans Picked Up | 7/12/2022 | APPLICANT |
| Disabled Access Plans Picked Up | 7/12/2022 | APPLICANT |
| Applicant returned to address corrections | 1/20/2023 | REZA HAGHIGHAT |
| Plan Check Approved | 1/26/2023 | REZA HAGHIGHAT |
| Issued | 6/7/2023 | APPLICANT |
| Permit Finaled | 3/11/2026 | CASIMIR BRITTON |
Permit Application Clearance Information
| Specific Plan | Cleared | 1/10/2023 | ALESSANDRO MERCURI |
| ZA Case | Cleared | 1/10/2023 | ANACANY HURTADO |
| ZA Case | Cleared | 1/10/2023 | ANACANY HURTADO |
| Address approval | Cleared | 1/11/2023 | ANTHONY MAINEZ |
| DAS Clearance | Cleared | 1/12/2023 | SHINE LIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2023 | ANTHONY MAINEZ |
Contact Information
| Architect | Azadi,, Bijan; Lic. No.: C18972 | 2825 PLAZA DEL AMO # 179 TORRANCE, CA 90503 |
| Contractor | Concord Construction Inc; Lic. No.: 1077056-B | 449 SOUTH BEVERLY DRIVE 1ST FLOOR BEVERLY HILLS, CA 90212 |
Inspector Information
| CASIMIR BRITTON, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
| SHAVONNE ESPINOZA, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/14/2023 | Corrections Issued | GRANT WOODS |
| Pre-Inspection | 8/23/2023 | Approved | SORIN CIRSTOIU |
| Pre-Inspection | 9/29/2023 | Corrections Issued | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 10/12/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Footing/Foundation/Slab | 10/12/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Excavation/Setback/Form/Re-Bar | 10/16/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Excavation/Setback/Form/Re-Bar | 11/3/2023 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Excavation/Setback/Form/Re-Bar | 11/6/2023 | Not Ready for Inspection | CASIMIR BRITTON |
| Excavation/Setback/Form/Re-Bar | 11/8/2023 | Approved | CASIMIR BRITTON |
| Footing/Foundation/Slab | 11/14/2023 | Not Ready for Inspection | CASIMIR BRITTON |
| Excavation/Setback/Form/Re-Bar | 11/16/2023 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Footing/Foundation/Slab | 11/16/2023 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Excavation/Setback/Form/Re-Bar | 11/20/2023 | Approved | MICHAEL PETRUSKO |
| Footing/Foundation/Slab | 11/20/2023 | Approved | MICHAEL PETRUSKO |
| Footing/Foundation/Slab | 12/5/2023 | Approved | MICHAEL PETRUSKO |
| Masonry Wall/Backfill | 12/5/2023 | Approved | MICHAEL PETRUSKO |
| Footing/Foundation/Slab | 1/2/2024 | Partial Inspection | CASIMIR BRITTON |
| Masonry Wall/Backfill | 1/2/2024 | Partial Approval | CASIMIR BRITTON |
| Masonry Wall/Backfill | 2/16/2024 | Conditional Approval | CASIMIR BRITTON |
| Reinforced Concrete Frame | 2/16/2024 | Partial Inspection | CASIMIR BRITTON |
| Special/Order Compliance | 2/16/2024 | Partial Inspection | CASIMIR BRITTON |
| Deputy Drilled-In Anchors | 2/29/2024 | Conditional Approval | SHAVONNE ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 3/1/2024 | Partial Approval | CASIMIR BRITTON |
| Deputy Reinf. Masonry | 3/6/2024 | Conditional Approval | SHAVONNE ESPINOZA |
| Deputy Steel/Welding | 5/15/2024 | Conditional Approval | CASIMIR BRITTON |
| Wood Frame | 5/21/2024 | Corrections Issued | CASIMIR BRITTON |
| Wood Frame | 6/14/2024 | Corrections Issued | CASIMIR BRITTON |
| Pre-Inspection | 7/3/2024 | Partial Inspection | CASIMIR BRITTON |
| Wood Frame | 7/10/2024 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Wood Frame | 7/11/2024 | No Access for Inspection | GRANT WOODS |
| Wood Frame | 7/15/2024 | Approved | CASIMIR BRITTON |
| Drywall Nailing | 9/16/2024 | Corrections Issued | GRANT WOODS |
| Special/Order Compliance | 9/16/2024 | Corrections Issued | GRANT WOODS |
| Drywall Nailing | 9/27/2024 | Not Ready for Inspection | CASIMIR BRITTON |
| Special/Order Compliance | 9/27/2024 | No Access for Inspection | GRANT WOODS |
| Drywall Nailing | 10/1/2024 | Not Ready for Inspection | CASIMIR BRITTON |
| Drywall Nailing | 1/17/2025 | Partial Approval | CASIMIR BRITTON |
| Final | 1/9/2026 | No Access for Inspection | CASIMIR BRITTON |
| SGSOV-Seismic Gas S/O Valve | 1/9/2026 | SGSOV Not Ready | CASIMIR BRITTON |
| Smoke Detectors | 1/9/2026 | No Access for Inspection | CASIMIR BRITTON |
| Final | 3/11/2026 | Permit Finaled | CASIMIR BRITTON |
| SGSOV-Seismic Gas S/O Valve | 3/11/2026 | SGSOV Approved | CASIMIR BRITTON |
| Smoke Detectors | 3/11/2026 | Approved | CASIMIR BRITTON |