575 N HANLEY AVE 90049
Certificate Information: 575 N HANLEY AVE 90049
- Application / Permit
- 22016-30000-16639
- Plan Check / Job No.
- B22WL02225
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- exterior and interior remodel to a portion of an existing 1-story S.F.R., including minor exterior window modifications. building footprint, height & envelope remains unchanged. zero increase in sqft.
- Permit Issued
- Issued on 11/14/2022
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 4/8/2024
Permit Application Status History
| Submitted | 6/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2022 | JASON JANGADA |
| Corrections Issued | 6/15/2022 | JASON JANGADA |
| Applicant returned to address corrections | 6/27/2022 | JASON JANGADA |
| Plan Check Approved | 7/1/2022 | JASON JANGADA |
| Building Plans Picked Up | 7/5/2022 | APPLICANT |
| Issued | 11/14/2022 | APPLICANT |
| Permit Finaled | 4/8/2024 | EVAN COOPER |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Ogosta,, Edward Thomas; Lic. No.: C30480 | 11157 BARMAN AVENUE CULVER CITY, CA 90230 |
| Contractor | Combined Construction Services Inc; Lic. No.: 808265-B | 810 WEST HYDE PARK BLVD INGLEWOOD, CA 90302 |
| Engineer | Ekmekji,, Steve Eli; Lic. No.: C66727 | 19281 BERCLAIR LANE TARZANA, CA 91356 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/8/2022 | Partial Inspection | DAVID FEILER |
| Pre-Inspection | 12/14/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 4/13/2023 | Corrections Issued | KEVIN SARGSYAN |
| Deputy Wood Construction | 4/13/2023 | Conditional Approval | KEVIN SARGSYAN |
| HVAC-Rough | 6/7/2023 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 6/7/2023 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 6/14/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 6/14/2023 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 6/21/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 6/21/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 7/6/2023 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 7/6/2023 | Partial Approval | KEVIN SARGSYAN |
| Shower Pan | 7/6/2023 | Approved | KEVIN SARGSYAN |
| Insulation | 7/13/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Insulation | 7/20/2023 | Corrections Issued | KEVIN SARGSYAN |
| Insulation | 7/24/2023 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 8/1/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 8/15/2023 | Partial Approval | ARAM AVEDISIAN |
| Final | 2/14/2024 | Corrections Issued | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 2/14/2024 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 2/14/2024 | Approved | CARLOS MATAMOROS |
| Final | 4/8/2024 | Permit Finaled | EVAN COOPER |