575 N HANLEY AVE 90049

Certificate Information: 575 N HANLEY AVE 90049

Application / Permit
22016-30000-16639
Plan Check / Job No.
B22WL02225
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
exterior and interior remodel to a portion of an existing 1-story S.F.R., including minor exterior window modifications. building footprint, height & envelope remains unchanged. zero increase in sqft.
Permit Issued
Issued on 11/14/2022
Issuing Office
Valley
Current Status
Permit Finaled on 4/8/2024

Permit Application Status History

Submitted 6/1/2022 APPLICANT
Assigned to Plan Check Engineer 6/13/2022 JASON JANGADA
Corrections Issued 6/15/2022 JASON JANGADA
Applicant returned to address corrections 6/27/2022 JASON JANGADA
Plan Check Approved 7/1/2022 JASON JANGADA
Building Plans Picked Up 7/5/2022 APPLICANT
Issued 11/14/2022 APPLICANT
Permit Finaled 4/8/2024 EVAN COOPER

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Ogosta,, Edward Thomas; Lic. No.: C30480 11157 BARMAN AVENUE      CULVER CITY, CA 90230
Contractor Combined Construction Services Inc; Lic. No.: 808265-B 810 WEST HYDE PARK BLVD      INGLEWOOD, CA 90302
Engineer Ekmekji,, Steve Eli; Lic. No.: C66727 19281 BERCLAIR LANE      TARZANA, CA 91356

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/8/2022 Partial Inspection DAVID FEILER
Pre-Inspection 12/14/2022 Approved GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 4/13/2023 Corrections Issued KEVIN SARGSYAN
Deputy Wood Construction 4/13/2023 Conditional Approval KEVIN SARGSYAN
HVAC-Rough 6/7/2023 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 6/7/2023 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 6/14/2023 Approved CARLOS MATAMOROS
PLUMBING-Rough 6/14/2023 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 6/21/2023 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 6/21/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 7/6/2023 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 7/6/2023 Partial Approval KEVIN SARGSYAN
Shower Pan 7/6/2023 Approved KEVIN SARGSYAN
Insulation 7/13/2023 Not Ready for Inspection KEVIN SARGSYAN
Insulation 7/20/2023 Corrections Issued KEVIN SARGSYAN
Insulation 7/24/2023 Approved KEVIN SARGSYAN
Drywall Nailing 8/1/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 8/15/2023 Partial Approval ARAM AVEDISIAN
Final 2/14/2024 Corrections Issued CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 2/14/2024 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 2/14/2024 Approved CARLOS MATAMOROS
Final 4/8/2024 Permit Finaled EVAN COOPER