8236 S ZITOLA TER 90293
Certificate Information: 8236 S ZITOLA TER 90293
- Application / Permit
- 22016-30000-14669
- Plan Check / Job No.
- B22WL01958
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel to an (E) Single Family Dwelling. Per Engineering Design.
- Permit Issued
- Issued on 1/10/2023
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 6/4/2025
Permit Application Status History
| Submitted | 5/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2022 | ALFREDO JARA |
| Corrections Issued | 5/24/2022 | ALFREDO JARA |
| Applicant returned to address corrections | 7/26/2022 | DAVID CASTILLO |
| Applicant returned to address corrections | 8/24/2022 | DAVID CASTILLO |
| Applicant returned to address corrections | 10/6/2022 | JASON JANGADA |
| Applicant returned to address corrections | 10/26/2022 | ALFREDO JARA |
| Applicant returned to address corrections | 10/26/2022 | RICHARD GARCIA |
| Building Plans Picked Up | 10/28/2022 | APPLICANT |
| Applicant returned to address corrections | 12/13/2022 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 12/28/2022 | AMY GUEVARRA |
| Plan Check Approved | 12/30/2022 | AMY GUEVARRA |
| Issued | 1/10/2023 | APPLICANT |
| Permit Finaled | 6/3/2025 | JESUS PINEDA |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/26/2022 | STEVEN JIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/7/2022 | HISASHI KOBAYAKAWA |
| Grading Pre-Inspection | Cleared | 12/13/2022 | JOHNPAUL ISIP |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Alferez,, Vicente Narvaez; Lic. No.: C53875 | 460 E CARSON PLAZA DR STE 212 CARSON, CA 90746 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/6/2023 | Corrections Issued | KENNETH NAGLE |
| PLUMBING-Rough | 4/6/2023 | Partial Approval | KENNETH NAGLE |
| Footing/Foundation/Slab | 4/13/2023 | Approved | BOBBY KEY |
| Deputy Wood Construction | 12/13/2023 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2023 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 1/4/2024 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2024 | Partial Approval | BOBBY KEY |
| HVAC-Rough | 1/4/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 1/4/2024 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 1/25/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 1/25/2024 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 1/25/2024 | Partial Approval | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 1/25/2024 | Approved | BOBBY KEY |
| Insulation | 2/15/2024 | Partial Approval | HERBERT GIRON |
| Shower Pan | 2/15/2024 | Approved | HERBERT GIRON |
| Drywall Nailing | 3/13/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 3/13/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 1/24/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Final | 1/24/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| HVAC-Final | 1/24/2025 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 1/24/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 1/24/2025 | SGSOV Approved | TEMISTOCLES CAAL |
| Service/Power Release | 1/24/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Smoke Detectors | 1/24/2025 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 1/29/2025 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 1/29/2025 | Approved | TEMISTOCLES CAAL |
| Service/Power Release | 2/27/2025 | Approved | TEMISTOCLES CAAL |
| Final | 6/3/2025 | Permit Finaled | JESUS PINEDA |
| HVAC-Final | 6/3/2025 | Approved | JESUS PINEDA |
| Smoke Detectors | 6/3/2025 | Approved | JESUS PINEDA |