12109 W VENTURA PL 91604
Certificate Information: 12109 W VENTURA PL 91604
- Application / Permit
- 22016-30000-13726
- Plan Check / Job No.
- B22WL01828
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- Change of Use from Retail to Restaurant (3,892 sf) ground level and mezzanine (1086 sf), add demising walls to create 3 separate tenant spaces add accessible restrooms. Core & Shell only, T.I. under separate permits. ; Unit A ; A-2 Occupancy w./ 74 Occupants ; 1st floor = 1,442 ; Mezzanine = 506 sf ; Unit B ; A-2 Occupancy w./ 89 Occupants ; 1st floor = 1,718 ; Mezzanine = 580 sf ; Unit C ; A-2 Occupancy w./ 32 Occupants ; 1st floor = 732 ; No Mezzanine ;
- Permit Issued
- Issued on 3/20/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2022 | REZA HAGHIGHAT |
| Corrections Issued | 6/7/2022 | REZA HAGHIGHAT |
| Disabled Access Plans Picked Up | 6/15/2022 | APPLICANT |
| Quality Review Completed | 6/16/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 1/3/2023 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 1/10/2023 | REZA HAGHIGHAT |
| Plan Check Approved | 3/15/2023 | REZA HAGHIGHAT |
| Issued | 3/20/2023 | APPLICANT |
| CofO in Progress | 2/12/2025 | STEVEN LEVITT |
| Permit Finaled | 2/24/2025 | JEFFREY DURAN |
| CofO Issued | 2/24/2025 | JEFFREY DURAN |
| Permit Finaled | 2/24/2025 | JEFFREY DURAN |
Permit Application Clearance Information
| ZA Case | Cleared | 8/25/2022 | DANG NGUYEN |
| Address approval | Cleared | 8/26/2022 | DAGOVERTO GUERRERO |
| Highway dedication | Cleared | 8/26/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/26/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/1/2022 | DAGOVERTO GUERRERO |
| Specific Plan | Cleared | 12/12/2022 | ADRINEH MELKONIAN |
| Specific Plan | Cleared | 12/14/2022 | BRANDON WILSON |
| Food Service Establishment | Cleared | 12/28/2022 | PAWAN VERMA |
| DAS Clearance | Cleared | 3/10/2023 | EDDIE GARIN |
| Food establishment approval | Cleared | 3/15/2023 | LACDHS APPROVED |
Contact Information
| Architect | Rocha,, Carlos Joel; Lic. No.: C19775 | 28025 DOROTHY DRIVE SUITE 206 AGOURA HILLS, CA 91301 |
| Contractor | Rocha Nuez Abdoh Construction Inc; Lic. No.: 791474-B | 28025 DOROTHY DRIVE 100 AGOURA HILLS, CA 91301 |
| Engineer | Kazemi,, Milad; Lic. No.: C92143 | 21126 MERRIDY STREET CHATSWORTH, CA 91311 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/27/2023 | Partial Inspection | CAMERON CHABAN |
| Drywall Nailing | 11/7/2023 | Partial Approval | ROBERT DAVIS |
| Wood Frame | 11/7/2023 | Partial Approval | ROBERT DAVIS |
| Footing/Foundation/Slab | 11/13/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Deputy Reinf. Concrete | 9/19/2024 | Conditional Approval | STEVEN LEVITT |
| Footing/Foundation/Slab | 9/20/2024 | Approved | STEVEN LEVITT |
| Deputy Reinf. Concrete | 9/23/2024 | Conditional Approval | CAMERON CHABAN |
| Wood Frame | 10/22/2024 | Approved | STEVEN LEVITT |
| Structural Steel Frame | 11/15/2024 | Approved | STEVEN LEVITT |
| Interior/Exterior Lathing | 12/16/2024 | Approved | STEVEN LEVITT |
| Drywall Nailing | 1/23/2025 | Approved | STEVEN LEVITT |
| Final | 1/23/2025 | Not Ready for Inspection | STEVEN LEVITT |
| Reinforced Masonry Frame | 1/23/2025 | Approved | STEVEN LEVITT |
| SGSOV-Seismic Gas S/O Valve | 1/23/2025 | SGSOV Not Ready | STEVEN LEVITT |
| Smoke Detectors | 1/23/2025 | Not Ready for Inspection | STEVEN LEVITT |
| Final | 1/29/2025 | OK to Issue CofO | STEVEN LEVITT |
| SGSOV-Seismic Gas S/O Valve | 1/29/2025 | SGSOV Approved | STEVEN LEVITT |
| Smoke Detectors | 1/29/2025 | Approved | STEVEN LEVITT |