3509-3511 W 17TH ST 90019

Certificate Information: 3509-3511 W 17TH ST 90019

Application / Permit
22016-30000-13174
Plan Check / Job No.
B22WL01681
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Convert (e) rec-room (610 sf) and storage (177 sf) room at 1st floor of (e) 2-story SFD (1,186 sf) over 3-car garage (500 sf) to ADU (787 sf) per LAMC 12.22 A.33(c) and (e) ; convert SFD to a duplex by enclosing the doorway in between ; Unit A = 593 sf ; 1 bedroom ; 1 bathroom ; Unit B = 593 sf ; 1 bedroom ; 1 bathroom ; ADU = 787 sf ; 2 bedrooms ; 1 bathroom
Permit Issued
Issued on 2/22/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2022 APPLICANT
Assigned to Plan Check Engineer 6/23/2022 REZA HAGHIGHAT
Corrections Issued 7/5/2022 REZA HAGHIGHAT
Quality Review Completed 7/18/2022 CHIHARU SUZUKI
Building Plans Picked Up 7/20/2022 APPLICANT
Plan Check Approved 2/17/2023 REZA HAGHIGHAT
Issued 2/22/2023 APPLICANT
CofO in Progress 12/1/2023 KATHRYN BUTTERWORTH
No Progress 12/4/2023 DEROLD HAUFF
CofO in Progress 12/14/2023 CHARLES BOGHOSKHAN
CofO Issued 12/15/2023 DEROLD HAUFF
Permit Finaled 12/15/2023 DEROLD HAUFF

Permit Application Clearance Information

Tenant Habitability Plan Cleared 10/4/2022 ISMAEL HERNANDEZ
Community Plan Implem. Overlay Cleared 10/25/2022 KYLE WINSTON
ZA Case Cleared 11/3/2022 DANIEL CORONADO
Hydrant and Access approval Cleared 11/18/2022 KURT CORRAL
Address approval Cleared 11/22/2022 TREVOR QUAN
Sewer availability Cleared 11/22/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 11/28/2022 TREVOR QUAN
Construction near power lines Cleared 12/17/2022 RIDWAN HARDY
DAS Clearance Cleared 2/10/2023 REZA HAGHIGHAT
Green Code Cleared 2/17/2023 REZA HAGHIGHAT

Contact Information

Architect Weston,, Jonathan Peter; Lic. No.: C34203 1916 WALCOTT WAY      LOS ANGELES, CA 90039
Contractor Owner-Builder       ,

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/8/2023 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 3/29/2023 Corrections Issued KATHRYN BUTTERWORTH
PLUMBING-Rough 3/29/2023 Corrections Issued KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 6/15/2023 Corrections Issued SCOTT FINNILA
ELECTRICAL-Rough 6/15/2023 Corrections Issued SCOTT FINNILA
Green Building Rough 6/15/2023 Corrections Issued SCOTT FINNILA
METHANE-Rough 6/15/2023 Not Ready for Inspection SCOTT FINNILA
PLUMBING-Rough 6/15/2023 Approved SCOTT FINNILA
Deputy Drilled-In Anchors 7/6/2023 Conditional Approval KATHRYN BUTTERWORTH
ELECTRICAL-Rough 7/11/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 7/11/2023 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 7/11/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 7/28/2023 Approved KATHRYN BUTTERWORTH
Drywall Nailing 7/28/2023 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Rough 7/28/2023 Approved KATHRYN BUTTERWORTH
Green Building Rough 7/28/2023 Approved KATHRYN BUTTERWORTH
METHANE-Rough 7/28/2023 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 7/28/2023 Approved KATHRYN BUTTERWORTH
Insulation 8/23/2023 Partial Approval STUART CHAPMAN
Wood Frame 8/23/2023 Corrections Issued STUART CHAPMAN
Drywall Nailing 8/31/2023 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Rough 8/31/2023 Approved KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 8/31/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Rough 8/31/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Shower Pan 9/14/2023 Approved KATHRYN BUTTERWORTH
Deputy Drilled-In Anchors 9/27/2023 Conditional Approval JUSTIN HAWLEY
Footing/Foundation/Slab 10/2/2023 Approved KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 10/13/2023 Approved CALEB MEISTER
Deputy Wood Construction 10/16/2023 Conditional Approval KATHRYN BUTTERWORTH
Insulation 10/23/2023 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 10/23/2023 Partial Approval KATHRYN BUTTERWORTH
Final 11/13/2023 Corrections Issued KATHRYN BUTTERWORTH
Green Building Final 11/13/2023 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 11/13/2023 SGSOV Not Ready KATHRYN BUTTERWORTH
Smoke Detectors 11/13/2023 Approved KATHRYN BUTTERWORTH
Final 11/15/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 11/15/2023 SGSOV Approved KATHRYN BUTTERWORTH
Final 11/28/2023 OK to Issue CofO KATHRYN BUTTERWORTH