128 1/2 N RIDGEWOOD PL 90004

Certificate Information: 128 1/2 N RIDGEWOOD PL 90004

Application / Permit
22016-30000-13065
Plan Check / Job No.
B22WL01645
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of (E) detached garage to ADU per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 12/6/2022
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/28/2022 APPLICANT
Assigned to Plan Check Engineer 4/29/2022 DAVID CASTILLO
Corrections Issued 5/3/2022 DAVID CASTILLO
Applicant returned to address corrections 8/21/2022 KAVIAN REFAHI
Applicant returned to address corrections 9/2/2022 DAVID CASTILLO
Building Plans Picked Up 9/6/2022 APPLICANT
Plan Check Approved 9/16/2022 JASON JANGADA
Issued 12/6/2022 APPLICANT
CofO in Progress 8/31/2023 JEFFREY MEAD
Permit Finaled 9/25/2023 DEROLD HAUFF
CofO Issued 9/25/2023 DEROLD HAUFF
Permit Finaled 9/25/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/13/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 7/13/2022 JEANIE LAM
Sewer availability Cleared 7/14/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 7/15/2022 JEANIE LAM

Contact Information

Contractor Everest Building & Remodeling Inc; Lic. No.: 1053298-B 4154 WEST 162ND ST      LAWNDALE, CA 90260
Engineer Kim,, Taewon; Lic. No.: C80632 2320 SANTA CRUZ CT      TORRANCE, CA 90501

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/31/2023 Approved JEFFREY MEAD
Underground Mechanical 2/7/2023 Partial Approval JEFFREY MEAD
Footing/Foundation/Slab 2/14/2023 Conditional Approval FREDDIE RIVERA
Footing/Foundation/Slab 2/21/2023 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 4/14/2023 Approved MICHAEL LEWIS
HVAC-Rough 4/14/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 4/14/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 4/19/2023 Approved JEFFREY MEAD
Insulation 4/27/2023 Corrections Issued LILIANA PORTILLO
Drywall Nailing 5/5/2023 Approved JEFFREY MEAD
Interior/Exterior Lathing 5/12/2023 Approved JEFFREY MEAD
Interior/Exterior Lathing 6/9/2023 Approved JEFFREY MEAD
ELECTRICAL-Final 6/30/2023 Corrections Issued JEFFREY MEAD
ELECTRICAL-Final 7/20/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 8/9/2023 Corrections Issued JEFFREY MEAD
HVAC-Final 8/23/2023 Approved JEFFREY MEAD
ELECTRICAL-Final 8/30/2023 Approved JEFFREY MEAD
Final 8/30/2023 OK to Issue CofO JEFFREY MEAD
PLUMBING-Final 8/30/2023 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 8/30/2023 SGSOV Approved JEFFREY MEAD
Smoke Detectors 8/30/2023 Approved JEFFREY MEAD