2127 S WALNUT AVE 90291

Certificate Information: 2127 S WALNUT AVE 90291

Application / Permit
22016-30000-12811
Plan Check / Job No.
B22WL01582
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION AND ADDITION OF EXISTING DETACHED GARAGE INTO ADU AND INCREASE ROOF HEIGHT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g)
Permit Issued
Issued on 8/30/2022
Issuing Office
Current Status
CofO Issued on 8/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2022 APPLICANT
Assigned to Plan Check Engineer 4/29/2022 JASON JANGADA
Corrections Issued 5/2/2022 JASON JANGADA
Applicant returned to address corrections 6/14/2022 JASON JANGADA
Plan Check Approved 8/11/2022 JASON JANGADA
Issued 8/30/2022 APPLICANT
Building Plans Picked Up 9/6/2022 APPLICANT
CofO in Progress 8/15/2023 HERBERT GIRON
Permit Finaled 8/16/2023 DANIEL ORRANTE
CofO Issued 8/16/2023 DANIEL ORRANTE
Permit Finaled 8/16/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/8/2022 DINAH GARIN
Sewer availability Cleared 6/8/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 6/10/2022 DINAH GARIN
Specific Plan Cleared 7/12/2022 PEDRO AYALA
Construction near power lines Cleared 8/4/2022 RIDWAN HARDY

Contact Information

Contractor G K L Builders; Lic. No.: 892592-B 2460 GLENCOE AVE      VENICE, CA 90291
Engineer Garcia,, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/21/2022 Corrections Issued DAVID FEILER
PLUMBING-Rough 11/23/2022 Partial Approval DAVID FEILER
Footing/Foundation/Slab 11/30/2022 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 1/24/2023 Conditional Approval HERBERT GIRON
ELECTRICAL-Rough 2/24/2023 Approved EVAN COOPER
HVAC-Rough 2/24/2023 Corrections Issued EVAN COOPER
PLUMBING-Rough 2/24/2023 Approved EVAN COOPER
Special/Order Compliance 2/24/2023 Corrections Issued EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 3/8/2023 Partial Approval EVAN COOPER
Green Building Rough 3/8/2023 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 3/22/2023 Conditional Approval EVAN COOPER
Green Building Rough 3/22/2023 Partial Approval EVAN COOPER
Interior/Exterior Lathing 3/22/2023 Partial Approval EVAN COOPER
Insulation 3/24/2023 Corrections Issued EVAN COOPER
Drywall Nailing 3/30/2023 Approved HERBERT GIRON
Insulation 3/30/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 3/30/2023 Approved HERBERT GIRON
Shower Pan 3/30/2023 Approved HERBERT GIRON
ELECTRICAL-Final 6/13/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 6/15/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 8/8/2023 Approved HERBERT GIRON
Final 8/8/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 8/8/2023 Approved HERBERT GIRON
Green Building Final 8/8/2023 Approved HERBERT GIRON
Green Building Rough 8/8/2023 Approved HERBERT GIRON
HVAC-Final 8/8/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 8/8/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 8/8/2023 SGSOV Not Required HERBERT GIRON
Smoke Detectors 8/8/2023 Approved HERBERT GIRON
Final 8/14/2023 OK to Issue CofO HERBERT GIRON
HVAC-Final 8/14/2023 Approved HERBERT GIRON