2433 N VENUS DR 90046

Certificate Information: 2433 N VENUS DR 90046

Application / Permit
22016-30000-11841
Plan Check / Job No.
B22WL01518
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior remodel AND ADDITION TO AN EXISTING 1-STORY SFD WITH ATTACHED GARAGE
Permit Issued
Issued on 9/9/2022
Issuing Office
Valley
Current Status
Issued on 9/9/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/18/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 TARIK SAOUD
Corrections Issued 5/4/2022 TARIK SAOUD
Quality Review Completed 5/9/2022 CHIHARU SUZUKI
Building Plans Picked Up 5/10/2022 APPLICANT
Plan Check Approved 9/6/2022 TARIK SAOUD
Issued 9/9/2022 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/27/2022 ROBERT HUGHES
Roof/Waste drainage to street Cleared 6/27/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/28/2022 WALLIE JONG

Contact Information

Contractor Revive Los Angeles Builders; Lic. No.: 1067952-B 10500 WYSTONE AVE      PORTER RANCH, CA 91326
Engineer Abkarian,, Raffi; Lic. No.: C36027 18763 VINTAGE STREET      NORTHRIDGE, CA 91324

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/18/2024 Conditional Approval BRIAN SULLIVAN
Footing/Foundation/Slab 10/24/2024 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 10/29/2024 Partial Approval RAUL BARAJAS
HVAC-Rough 6/12/2025 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 6/12/2025 Corrections Issued BRENDAN MORELLI
HVAC-Rough 7/30/2025 Approved BRENDAN MORELLI
PLUMBING-Rough 7/30/2025 Corrections Issued BRENDAN MORELLI
Interior/Exterior Lathing 8/1/2025 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 8/11/2025 Not Ready for Inspection ROY SPAULDING
ELECTRICAL-Rough 9/24/2025 Approved ROY SPAULDING
Insulation 9/30/2025 Corrections Issued ROY SPAULDING
BUILDING-Rough-Frame 11/4/2025 Not Ready for Inspection ROY SPAULDING
Green Building Rough 11/4/2025 Not Ready for Inspection ROY SPAULDING
Insulation 11/4/2025 Corrections Issued ROY SPAULDING
Wood Frame 11/4/2025 Not Ready for Inspection ROY SPAULDING
BUILDING-Rough-Frame 1/26/2026 Not Ready for Inspection ROY SPAULDING
Green Building Rough 1/26/2026 Approved ROY SPAULDING
PLUMBING-Rough 1/26/2026 Corrections Issued ROY SPAULDING
BUILDING-Rough-Frame 3/23/2026 Approved DAVID WILLIAMS
Drywall Nailing 4/7/2026 Approved ROY SPAULDING
Insulation 4/7/2026 Approved ROY SPAULDING
PLUMBING-Rough 4/7/2026 Approved ROY SPAULDING
HVAC-Rough 6/1/2026 No Access for Inspection ROY SPAULDING