2304 W EFFIE ST 90026

Certificate Information: 2304 W EFFIE ST 90026

Application / Permit
22016-30000-11233
Plan Check / Job No.
B22WL01400
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of storage area into an ADU. *** 1 of 2 ***
Permit Issued
Issued on 12/20/2022
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/15/2022 APPLICANT
Assigned to Plan Check Engineer 4/21/2022 RICHARD GARCIA
Corrections Issued 4/23/2022 RICHARD GARCIA
Plan Check Approved 12/8/2022 JOHNPAUL ISIP
Issued 12/20/2022 APPLICANT
CofO in Progress 12/19/2024 HAMIK HARTOUNIAN
Permit Finaled 12/31/2024 DEROLD HAUFF
CofO Issued 12/31/2024 DEROLD HAUFF
Permit Finaled 12/31/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/23/2022 STEVE MELGAR
Sewer availability Cleared 9/23/2022 STEVE MELGAR
Grading Pre-Inspection Cleared 9/28/2022 KIRK LINKLATER
Eng Process Fee Ord 176,300 Cleared 9/29/2022 STEVE MELGAR

Contact Information

Architect Daham,, Ramsey Walid; Lic. No.: C34257 127 ARENA STREET      EL SEGUNDO, CA 90245
Contractor Breakform Construction Inc; Lic. No.: 1092047-B 127 ARENA STREET      EL SEGUNDO, CA 90245
Engineer Alexander,, Andy; Lic. No.: C84086 1615 GRAMERCY AVE      TORRANCE, CA 90501

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/25/2023 Not Ready for Inspection THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 11/27/2023 Not Ready for Inspection THOMAS LOGRASSO
Deputy Wood Construction 12/22/2023 Conditional Approval BRENDAN MORELLI
Special/Order Compliance 1/2/2024 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Rough 1/12/2024 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 1/12/2024 Not Ready for Inspection THOMAS LOGRASSO
Special/Order Compliance 1/12/2024 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Rough 1/24/2024 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 1/24/2024 Approved THOMAS LOGRASSO
Sewer 1/24/2024 Approved THOMAS LOGRASSO
ELECTRICAL-Rough 3/11/2024 Corrections Issued THOMAS LOGRASSO
HVAC-Rough 3/11/2024 Not Ready for Inspection THOMAS LOGRASSO
Interior/Exterior Lathing 3/11/2024 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Rough 3/14/2024 Approved THOMAS LOGRASSO
HVAC-Rough 3/28/2024 Corrections Issued THOMAS LOGRASSO
HVAC-Rough 4/3/2024 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 5/13/2024 Approved ALIZAH MAYAGOITIA
Final 5/13/2024 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 5/13/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Rough 5/13/2024 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 5/13/2024 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 5/13/2024 Approved ALIZAH MAYAGOITIA
Final 9/24/2024 Partial Inspection HAMIK HARTOUNIAN
Green Building Final 9/24/2024 Approved HAMIK HARTOUNIAN
Final 12/18/2024 OK to Issue CofO HAMIK HARTOUNIAN