1913 S CLYDE AVE 90019
Certificate Information: 1913 S CLYDE AVE 90019
- Application / Permit
- 22016-30000-09773
- Plan Check / Job No.
- B22WL01231
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Addition to and conversion of a 3-car detached garage into an ADU per LAMC 12.22 A.33(c) and (d). maintaining 1-car garage for ADU ***SEE COMMENTS***
- Permit Issued
- Issued on 2/6/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 2/6/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/1/2022 | EDWIN ESPIN |
| Corrections Issued | 4/4/2022 | EDWIN ESPIN |
| Building Plans Picked Up | 4/6/2022 | APPLICANT |
| Applicant returned to address corrections | 11/14/2023 | RICHARD GARCIA |
| Plan Check Approved | 11/15/2023 | RICHARD GARCIA |
| Issued | 2/6/2025 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/4/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/4/2022 | RIDWAN HARDY |
| Sewer availability | Cleared | 8/3/2022 | JENSON LEE |
| Address approval | Cleared | 8/9/2022 | JENSON LEE |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2022 | JENSON LEE |
| Tenant Habitability Plan | Cleared | 11/9/2022 | MICHAEL SOTO |
Contact Information
| Contractor | F V Builders Inc; Lic. No.: 1082332-B | 6322 6TH AVE LOS ANGELES, CA 90043 |
| Engineer | Hughes,, Anthony; Lic. No.: C57339 | 420 N MCKINLEY ST STE 111-316 CORONA, CA 92879 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/20/2025 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Rough | 11/20/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Footing/Foundation/Slab | 12/1/2025 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 12/1/2025 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2026 | Partial Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 2/12/2026 | Partial Approval | BRENDAN MORELLI |
| Underground Mechanical | 2/12/2026 | Partial Approval | BRENDAN MORELLI |
| ELECTRICAL-Rough | 5/20/2026 | Corrections Issued | DAVID WILLIAMS |
| HVAC-Rough | 5/20/2026 | Corrections Issued | DAVID WILLIAMS |
| Interior/Exterior Lathing | 5/20/2026 | Partial Approval | DAVID WILLIAMS |
| PLUMBING-Rough | 5/20/2026 | Corrections Issued | DAVID WILLIAMS |