6210 S 10TH AVE 24-25 90043

Certificate Information: 6210 S 10TH AVE 24-25 90043

Application / Permit
22016-30000-08526
Plan Check / Job No.
B22WL01033
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert portion of (E) detached carport at the rear of the lot into two ADUs per CA G.C.S. 65852.2(e)(1)(D) and applicable part of LAMC 12.22A33(c)-(d), (g). One parking space to remain in (N) garage.
Permit Issued
Issued on 9/29/2022
Issuing Office
Metro
Current Status
CofO Issued on 2/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2022 APPLICANT
Assigned to Plan Check Engineer 3/18/2022 JAHANSHAH POURHASSAN
Corrections Issued 3/28/2022 JAHANSHAH POURHASSAN
Building Plans Picked Up 3/29/2022 APPLICANT
Plan Check Approved 8/1/2022 FERNANDO FLORES
Issued 9/29/2022 APPLICANT
CofO in Progress 1/31/2025 DARRYL ARNOLD
CofO in Progress 1/31/2025 DARRYL ARNOLD
Permit Finaled 2/26/2025 WINSTON DUNNING
CofO Issued 2/26/2025 WINSTON DUNNING
Permit Finaled 2/26/2025 WINSTON DUNNING

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/30/2022 JEANIE LAM
Address approval Cleared 6/13/2022 JEANIE LAM
Sewer availability Cleared 6/13/2022 JEANIE LAM
Construction near power lines Cleared 7/22/2022 RIDWAN HARDY

Contact Information

Architect Feld,, Dovid Yitzchak; Lic. No.: C37588 921 S HOLT AVENUE      LOS ANGELES, CA 90035
Architect Mcvay,, Bruce Cameron; Lic. No.: C11870 6440 E. EL ROBLE STREET      LONG BEACH, CA 90815
Contractor Oyz Developments Llc; Lic. No.: 1079567-B 1171 S ROBERTSON BLVD STE 101      LOS ANGELES, CA 90035

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/3/2023 Not Ready for Inspection ALAN MORELOS
Footing/Foundation/Slab 4/21/2023 Not Ready for Inspection DARRYL ARNOLD
Insulation 7/12/2023 Partial Approval ALAN MORELOS
Wood Frame 10/2/2023 Approved MARTIN TAVITIAN
Insulation 10/10/2023 Approved RICARDO ROBLES
Interior/Exterior Lathing 10/10/2023 Partial Approval RICARDO ROBLES
Drywall Nailing 10/19/2023 Approved RICARDO ROBLES
Interior/Exterior Lathing 10/19/2023 Approved RICARDO ROBLES
Special/Order Compliance 10/20/2023 Corrections Issued RICARDO ROBLES
Final 5/20/2024 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 5/20/2024 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 5/20/2024 Not Ready for Inspection DARRYL ARNOLD
Pre-Inspection 5/22/2024 Not Ready for Inspection DARRYL ARNOLD
Final 12/18/2024 Corrections Issued DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 12/18/2024 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 12/18/2024 Corrections Issued DARRYL ARNOLD
Final 1/27/2025 OK to Issue CofO DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 1/27/2025 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 1/27/2025 Approved DARRYL ARNOLD
Final 1/31/2025 OK to Issue CofO DARRYL ARNOLD
METHANE-Final 2/26/2025 Approved DARRYL ARNOLD