129-131 N OXFORD AVE 90004

Certificate Information: 129-131 N OXFORD AVE 90004

Application / Permit
22016-30000-08258
Plan Check / Job No.
B22WL01005
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERSION OF AN (E) STORAGE AREA IN A 3 STORY APARTMENT BUILDING INTO AN ADU PER GCS 65852.2(e)(1)(C). No demolition of interior walls.
Permit Issued
Issued on 12/5/2022
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2022 APPLICANT
Assigned to Plan Check Engineer 3/18/2022 JASON JANGADA
Corrections Issued 3/19/2022 JASON JANGADA
Building Plans Picked Up 3/22/2022 APPLICANT
Plan Check Approved 5/12/2022 RICARDO RAMIREZ
Issued 12/5/2022 APPLICANT
CofO in Progress 1/2/2024 RONALD JIMENEZ
Permit Finaled 1/2/2024 ERNESTO CORRAL
CofO Issued 1/2/2024 ERNESTO CORRAL
Permit Finaled 1/2/2024 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 4/8/2022 WALLIE JONG
Sewer availability Cleared 4/8/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 4/11/2022 WALLIE JONG
Historic Resource Verification Cleared 4/13/2022 MAX LODER
Redevelopment Project Area Cleared 4/28/2022 SUSAN WONG
ZI Cleared 4/28/2022 SUSAN WONG

Contact Information

Architect Feld,, Dovid Yitzchak; Lic. No.: C37588 921 S HOLT AVENUE      LOS ANGELES, CA 90035
Contractor Concord Construction Inc; Lic. No.: 1077056-B 449 SOUTH BEVERLY DRIVE   1ST FLOOR    BEVERLY HILLS, CA 90212

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 12/20/2022 No Access for Inspection RONALD JIMENEZ
Wood Frame 12/29/2022 Not Ready for Inspection TIMOTHY POWELL
Special/Order Compliance 12/30/2022 Corrections Issued TIMOTHY POWELL
Wood Frame 3/3/2023 Approved BRUCE CAMPBELL
Insulation 3/7/2023 Approved MARTIN TAVITIAN
Drywall Nailing 3/9/2023 Approved RONALD JIMENEZ
Interior/Exterior Lathing 3/9/2023 Approved RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 5/12/2023 SGSOV Not Ready MARTIN TAVITIAN
Final 5/16/2023 Partial Inspection RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 5/16/2023 SGSOV Approved RONALD JIMENEZ
Smoke Detectors 5/16/2023 Approved RONALD JIMENEZ
Final 12/22/2023 No Access for Inspection GREGORY POMISH
Final 12/29/2023 Conditional Approval RONALD JIMENEZ