2519 1/2 S HARCOURT AVE 90016
Certificate Information: 2519 1/2 S HARCOURT AVE 90016
- Application / Permit
- 22016-30000-08137
- Plan Check / Job No.
- B22WL00986
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE INTO AN ADU. PER GCS65852.2(e)(1)(A)
- Permit Issued
- Issued on 3/28/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 10/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/1/2022 | EDWIN ESPIN |
| Corrections Issued | 4/2/2022 | RICHARD GARCIA |
| Applicant returned to address corrections | 5/21/2022 | RICHARD GARCIA |
| Applicant returned to address corrections | 6/27/2022 | RICHARD GARCIA |
| Applicant returned to address corrections | 10/17/2022 | ALFREDO JARA |
| Building Plans Picked Up | 10/19/2022 | APPLICANT |
| Plan Check Approved | 3/28/2024 | ZENA HADDIS |
| Issued | 3/28/2024 | APPLICANT |
| CofO in Progress | 10/21/2024 | JUSTIN HAWLEY |
| Permit Finaled | 10/25/2024 | RUBEN SALAS |
| CofO Issued | 10/25/2024 | RUBEN SALAS |
| Permit Finaled | 10/25/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/12/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 5/12/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2022 | STEVE MELGAR |
| Address approval | Cleared | 2/7/2024 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/4/2024 | Corrections Issued | BRENDAN MORELLI |
| Pre-Inspection | 4/4/2024 | Partial Inspection | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 4/8/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Pre-Inspection | 4/8/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 4/9/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Pre-Inspection | 4/9/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 4/15/2024 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 4/15/2024 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 4/17/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 4/17/2024 | Approved | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 4/17/2024 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 4/17/2024 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 5/13/2024 | Corrections Issued | AMIR NAZARIAN |
| PLUMBING-Rough | 5/13/2024 | Corrections Issued | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 5/30/2024 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 5/30/2024 | Approved | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2024 | Partial Approval | JUSTIN HAWLEY |
| HVAC-Rough | 5/30/2024 | Corrections Issued | JUSTIN HAWLEY |
| MERV13>=Rough | 5/30/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Rough | 5/30/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 6/24/2024 | Approved | RICHARD DOCKUS |
| Green Building Rough | 6/26/2024 | Approved | JUSTIN HAWLEY |
| Insulation | 6/26/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 6/26/2024 | Partial Approval | JUSTIN HAWLEY |
| Drywall Nailing | 7/1/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 9/9/2024 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 10/4/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Final | 10/4/2024 | Corrections Issued | JUSTIN HAWLEY |
| HVAC-Final | 10/4/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| MERV13>=Final | 10/4/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 10/4/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 10/4/2024 | SGSOV Not Ready | JUSTIN HAWLEY |
| Smoke Detectors | 10/4/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| ELECTRICAL-Final | 10/17/2024 | Approved | JUSTIN HAWLEY |
| Final | 10/17/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| HVAC-Final | 10/17/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 10/17/2024 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 10/17/2024 | SGSOV Approved | JUSTIN HAWLEY |
| Smoke Detectors | 10/17/2024 | Approved | JUSTIN HAWLEY |
| Final | 10/21/2024 | OK to Issue CofO | JUSTIN HAWLEY |