11489 W CUMPSTON ST 91601

Certificate Information: 11489 W CUMPSTON ST 91601

Application / Permit
22016-30000-05979
Plan Check / Job No.
B22WL00778
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Garage conversion to ADU. Revise interior and exterior framing, replace roof framing, float concrete floor to curb level, new exterior door and windows, new interior finishes, new appliances, new casework, new mechanical, electrical, and plumbing.
Permit Issued
Issued on 5/8/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 11/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 RICHARD GARCIA
Corrections Issued 3/5/2022 RICHARD GARCIA
Applicant returned to address corrections 5/31/2022 RICHARD GARCIA
Applicant returned to address corrections 6/14/2022 RICHARD GARCIA
Plan Check Approved 6/15/2022 RICHARD GARCIA
No Progress 6/15/2022 RICHARD GARCIA
Plan Check Approved 6/29/2022 RICHARD GARCIA
Building Plans Picked Up 6/30/2022 APPLICANT
Issued 5/8/2023 APPLICANT
CofO in Progress 9/1/2023 JACK KARGODORIAN
Permit Finaled 11/28/2023 RUBEN SALAS
CofO Issued 11/28/2023 RUBEN SALAS
Permit Finaled 11/28/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/15/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 3/15/2022 CARLOS AGUILERA
Sewer availability Cleared 3/15/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/16/2022 CARLOS AGUILERA
ZI Cleared 3/17/2022 STEVEN WECHSLER

Contact Information

Contractor M Y Construction Inc; Lic. No.: 1036168-B 10116 HILLGROVE DRIVE      BEVERLY HILLS, CA 90210
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/15/2023 Conditional Approval MICHAEL SMITH
Excavation/Setback/Form/Re-Bar 5/18/2023 Approved JACK KARGODORIAN
PLUMBING-Rough 5/18/2023 Partial Approval JACK KARGODORIAN
Sewer 5/24/2023 Approved ARAM AVEDISIAN
HVAC-Rough 6/15/2023 Approved JACK KARGODORIAN
PLUMBING-Rough 6/15/2023 Corrections Issued JACK KARGODORIAN
BUILDING-Rough-Frame 6/28/2023 Not Ready for Inspection ROBERT GOLD
ELECTRICAL-Rough 6/28/2023 Approved ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 6/28/2023 Not Ready for Inspection ROBERT GOLD
Green Building Rough 6/28/2023 Approved ROBERT GOLD
MERV13>=Rough 6/28/2023 Approved ROBERT GOLD
PLUMBING-Rough 6/28/2023 Approved ROBERT GOLD
Wood Frame 6/28/2023 Not Ready for Inspection ROBERT GOLD
BUILDING-Rough-Frame 7/5/2023 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 7/5/2023 Approved JACK KARGODORIAN
Interior/Exterior Lathing 7/5/2023 Partial Approval JACK KARGODORIAN
Shower Pan 7/5/2023 Approved JACK KARGODORIAN
Wood Frame 7/5/2023 Approved JACK KARGODORIAN
Insulation 7/13/2023 Approved JACK KARGODORIAN
Interior/Exterior Lathing 7/13/2023 Approved JACK KARGODORIAN
Drywall Nailing 7/20/2023 Approved JACK KARGODORIAN
Underground Mechanical 7/27/2023 Approved JACK KARGODORIAN
ELECTRICAL-Final 8/23/2023 Corrections Issued MISAEL ESPARZA
Final 8/23/2023 Corrections Issued MISAEL ESPARZA
Green Building Final 8/23/2023 Approved MISAEL ESPARZA
HVAC-Final 8/23/2023 Corrections Issued MISAEL ESPARZA
MERV13>=Final 8/23/2023 Approved MISAEL ESPARZA
PLUMBING-Final 8/23/2023 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 8/23/2023 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 8/23/2023 Approved MISAEL ESPARZA
ELECTRICAL-Final 9/1/2023 Approved JACK KARGODORIAN
Final 9/1/2023 OK to Issue CofO JACK KARGODORIAN
HVAC-Final 9/1/2023 Approved JACK KARGODORIAN
Service/Power Release 9/1/2023 Approved JACK KARGODORIAN